Who to call and what to check for a solar, wind, or battery storage project in Mitchell County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.

Who handles property records and taxes in Mitchell County?

The Mitchell County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.

Mitchell County directory (Texas Comptroller)Lease rates and rollback taxes

Which TCEQ office covers Mitchell County?

TCEQ Region 3, Abilene
1977 Industrial Blvd, Abilene TX 79602-7833
Main line: 325-698-9674 · Spills, 24 hours: 800-832-8224

Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.

TCEQ region directoryConstruction stormwater permit

Does Mitchell County have zoning or a solar permit?

Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.

What energy projects are proposed in Mitchell County?

ERCOT's August 2026 interconnection report lists 15 proposed energy projects in Mitchell County (4 solar, 2 wind and 9 battery storage), about 6,792 MW in all. 5 of the 15 have a signed interconnection agreement.

Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.

Scroll the table sideways to see every column.

Project and connection pointDeveloperTypeMWProjected in serviceStage
Zeus Spade BESSTap 345 kV 1030 Morgan Creek to 76030 Gasconades CreekSpade BESSBattery storage (paired with wind)446.3Mar 2028Under construction
Zeus Spade WindTap 345 kV 1030 Morgan Creek to 76030 Gasconades CreekSpade Wind, LLCWind987.3Mar 2028Under construction
Zeus Mitchell BESSTap 345 kV 10049 Ranger Camp - 10057 Prong Moss CKT #01 and #02Mitchell BESSBattery storage (paired with solar)1,042.9Apr 2029Under construction
Zeus Mitchell SolarTap 345 kV 10049 Ranger Camp - 10057 Prong Moss CKT #01 and #02Mitchell Solar, LLCSolar804.7Apr 2029Under construction
Hackberry Creek Solartap 345kV 10053 Cattleman Switch - 1058 Longshore SwitchHackberry Creek Solar LLCSolar175.5Jan 2028Signed; security posted
Zeus Mitchell BESS IITap 345 kV 10049 Ranger Camp - 10057 Prong Moss CKT #01 and #02Zeus Mitchell BESS II, LLCBattery storage (paired with solar)1,042.9May 2027In study
Sepik BESStap 138kV 11342 Loraine South – 10050 Ranger CampBRP Sepik BESS LLCBattery storage (stand-alone)205.0Mar 2028In study
Johnson Grass SolarTap 138kV (#11395) Navigation - (#10054) CattlemenJohnson Grass Solar ,LLCSolar195.8Apr 2028In study
Dolce BESSTap 138kV 1189 BARBER_LK1_8 - 19520 CHINAGRVX2_8Dolce BESS, LLCBattery storage (stand-alone)100.7Jan 2029In study
Prairie Power WindTap 345 kV Longshore Switch (Bus# 1058) to Cattleman Switch (Bus# 1...Prairie Power Wind, LLCWind302.9Apr 2029In study
Sunflower Valley Storage1414 Champion Creek Substation 345 kVSunflower Valley Storage, LLCBattery storage (stand-alone)205.7Apr 2029In study
Whitetail BESStap Salt Mine (#23846) to Bulldog (#23833) 138kVHunt Energy Network, LLCBattery storage (stand-alone)180.0Jun 2029In study
Rabbit Hollow Energy Storage1190 Barber Lake Switch 138kVRabbit Hollow Energy Storage, LLCBattery storage (stand-alone)341.8Dec 2029In study
Rosenix SolarCattleman (#10053) – Gasconades (#76030)Rosenix Solar, LLCSolar510.0Dec 2029In study
Rosenix StorageMORGAN CREEK (#1030) - GASCONADES (#76030)Rosenix Solar, LLCBattery storage (paired with solar)250.0Dec 2029In study

Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.

Where are the flood maps for Mitchell County?

FEMA flood maps for Mitchell County

How does a project here connect to the grid?

Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.

Interconnection by market and utilityERCOT resource integration

What state and federal reviews can apply?

Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.

Statewide and federal contactsTexas decommissioning law

Check a specific property in Mitchell County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Open Quicksand Check

Other counties served by TCEQ Region 3

Archer · Baylor · Brown · Callahan · Clay · Coleman · Comanche · Cottle · Eastland · Fisher · Foard · Hardeman · Haskell · Jack · Jones · Kent · Knox · Montague · Nolan · Runnels · Scurry · Shackelford · Stephens · Stonewall · Taylor · Throckmorton · Wichita · Wilbarger · Young

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not legal advice. Found an error? Let us know.