Haskell County, Texas: solar, wind, and storage permits

Contacts checked 2026-09-26 · From official state and federal directories

Who to call and what to check for a solar, wind, or battery storage project in Haskell County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.

Who handles property records and taxes in Haskell County?

The Haskell County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.

Haskell County directory (Texas Comptroller)Lease rates and rollback taxes

Which TCEQ office covers Haskell County?

TCEQ Region 3, Abilene
1977 Industrial Blvd, Abilene TX 79602-7833
Main line: 325-698-9674 · Spills, 24 hours: 800-832-8224

Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.

TCEQ region directoryConstruction stormwater permit

Does Haskell County have zoning or a solar permit?

Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.

What energy projects are proposed in Haskell County?

ERCOT's August 2026 interconnection report lists 17 proposed energy projects in Haskell County (10 solar, 2 wind and 5 battery storage), about 3,976 MW in all. 9 of the 17 have a signed interconnection agreement, and 5 have been energized or approved to connect.

Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.

Scroll the table sideways to see every column.

Project and connection pointDeveloperTypeMWProjected in serviceStage
Quantum Solar60089 Kilby Station 345kVIP QUANTUM II, LLCSolar321.7Sep 2026Approved to connect
Quantum Storage60089 Kilby Switching Station 345kVIP Quantum II BESS, LLCBattery storage321.8Sep 2026Approved to connect
Solace Solartap 345kV 1430 Graham - 1048 TonkawasIP QUANTUM, LLC.Solar321.6Sep 2026Approved to connect
Solace Storagetap 345kV 1430 Graham - 1048 TonkawasIP Quantum BESS, LLCBattery storage321.8Sep 2026Approved to connect
Millers Branch Solar IIITap 345kV 60703 Gauss - 60514 Clear Crossing (60712 QUASAR)Miller's Branch Solar LLCSolar133.0Oct 2026Approved to connect
Rubicon Alpha Wind60507 pendulo7A 345kVThrockmorton Wind, LLCWind222.6Jul 2027Signed; security posted
Briggs Solartap 345kV 60515 Clear Crossing - 60507 PenduloIP Quantum III, LLCSolar323.7Apr 2028Signed; security posted
Briggs Storagetap 345kV 60515 Clear Crossing - 60507 PenduloIP Quantum III, LLCBattery storage (paired with solar)336.0Apr 2028Signed; security posted
Inertia Solartap 345kV 60515 Clear Crossing - 6104 Smoky HillInertia Solar Project, LLCSolar202.4Mar 2029Signed; security posted
Journey SolarTap 138kV Paint Creek 6161 - Aspermont 6158Journey Solar, LLCSolar124.7Sep 2027In study
Rolling Plains BESS6104 SMOKY HILL 345kVHaskell County BESS LLCBattery storage (stand-alone)120.0Jun 2028In study
Grasshopper SolarSmoky Hill 345kV Sub (Bus #6104) Locational coordinates : 33.34414;...Grasshopper Solar LLCSolar407.7Oct 2028In study
Blue Spring Solar#60515 Clear Crossing 345 kVFlat Creek Solar, LLCSolar301.0Oct 2028In study
DMF Sagerton Solar SLFTap 138kV 6158 Aspermont – 6161 Paint CreekDouble Mountain Fork LLCSolar125.5Dec 2028In study
DMF Sagerton Storage SLFTap 138kV 6158 Aspermont – 6161 Paint CreekDouble Mountain Fork LLCBattery storage (paired with solar)Self-limitingDec 2028In study
Max 4 WindTap 345 kV Gauss7D (Bus# 60703) to Quasar7A (Bus# 60712) Transmissi...Lake Creek Wind, LLCWind352.6Aug 2029In study
Lueders SolarTap 138kV 6161 Paint Creek - 6200 Ft PhantomInnovative Solar 75Solar40.0Dec 2029In study

Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.

Where are the flood maps for Haskell County?

FEMA flood maps for Haskell County

How does a project here connect to the grid?

Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.

Interconnection by market and utilityERCOT resource integration

What state and federal reviews can apply?

Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.

Statewide and federal contactsTexas decommissioning law

Check a specific property in Haskell County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Open Quicksand Check

Other counties served by TCEQ Region 3

Archer · Baylor · Brown · Callahan · Clay · Coleman · Comanche · Cottle · Eastland · Fisher · Foard · Hardeman · Jack · Jones · Kent · Knox · Mitchell · Montague · Nolan · Runnels · Scurry · Shackelford · Stephens · Stonewall · Taylor · Throckmorton · Wichita · Wilbarger · Young

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not legal advice. Found an error? Let us know.