Comanche County, Texas: solar, wind, and storage permits

Contacts checked 2026-09-26 · From official state and federal directories

Who to call and what to check for a solar, wind, or battery storage project in Comanche County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.

Who handles property records and taxes in Comanche County?

The Comanche County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.

Comanche County directory (Texas Comptroller)Lease rates and rollback taxes

Which TCEQ office covers Comanche County?

TCEQ Region 3, Abilene
1977 Industrial Blvd, Abilene TX 79602-7833
Main line: 325-698-9674 · Spills, 24 hours: 800-832-8224

Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.

TCEQ region directoryConstruction stormwater permit

Does Comanche County have zoning or a solar permit?

Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.

What energy projects are proposed in Comanche County?

ERCOT's August 2026 interconnection report lists 10 proposed energy projects in Comanche County (4 solar and 6 battery storage), about 2,798 MW in all. 4 of the 10 have a signed interconnection agreement.

Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.

Scroll the table sideways to see every column.

Project and connection pointDeveloperTypeMWProjected in serviceStage
Lamkin Solartap 69kV 258 Hamilton - 273 GustineCommanche Solar, LLCSolar101.5Aug 2027Signed; security posted
Darkwood SolarTap 345KV 1900 Comanche Peak to 1440 Comanche SSMustang Creek Solar, LLCSolar152.0Sep 2027Signed; security posted
Darkwood BESSTap 345KV 1900 Comanche Peak - 1440 Comanche SwitchMustang Creek Solar, LLCBattery storage (paired with solar)150.5Jul 2028Signed; security posted
Comanche BESS#1440 Comanche Switching Station 345kVENERGOS BESSBattery storage (stand-alone)614.4May 2029Signed Mar 2026
Dragan Solar1440 Comanche 345kVHecate Comanche Solar LLCSolar411.0Sep 2027In study
Crios BESSTap 138 kV 1649 HASSE_P8 - 1684 SABANA_8BRP Crios BESS LLCBattery storage (stand-alone)205.5Mar 2028In study
Merope BESS345 kV Corn Trail Switch Substation (#11441)BRP Merope BESS LLCBattery storage (stand-alone)402.4Mar 2028In study
Saddle Horn Station BESS SLFtap 138kV 1650 COMANCHE_T8 - 290SHILOHCSaddle Horn Station BESS LLCBattery storage (paired with solar)177.4Sep 2028In study
Saddle Horn Station Solar SLF1650 COMANCHE_T8 - 290 SHILOHC 138 kV LineSaddle Horn Station LLCSolar174.6Sep 2028In study
Dragan Storage1440 Comanche 345kVHecate Grid Dragan Storage LLCBattery storage (paired with solar)408.3Mar 2030In study

Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.

Where are the flood maps for Comanche County?

FEMA flood maps for Comanche County

How does a project here connect to the grid?

Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.

Interconnection by market and utilityERCOT resource integration

What state and federal reviews can apply?

Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.

Statewide and federal contactsTexas decommissioning law

Check a specific property in Comanche County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Open Quicksand Check

Other counties served by TCEQ Region 3