Interconnection by electricity market and utility

Updated September 26, 2026 · Market steps checked against live sources where marked

Every solar, wind, or storage project needs permission to connect to the grid, and it is often the longest and most expensive step. Who you apply to depends on the project's size and where it is.

Two paths. Small projects that connect to local distribution lines (in Texas, generally under 10 MW and below 60 kV) apply to the local utility. Large projects that connect to high-voltage transmission apply through the regional grid operator's queue (ERCOT, SPP, MISO, and others) and work with the transmission owner.

Texas utilities: where to apply

Your electric bill names your delivery utility. Distribution interconnection in Texas follows PUCT rules 25.211 and 25.212. The PUC has been drafting revisions (Project 54233, including a new rule 25.210 for projects over 250 kW); see the May 2025 discussion draft and check the PUC for its current status.

Oncor
ERCOT · Dallas–Fort Worth and much of North, Central, and West Texas
Applications through the eTRACK portal; separate forms for systems 500 kW and larger and for projects registering with ERCOT (under 10 MW, below 60 kV). Email: dg@oncor.comFor installers and developers500 kW+ application (PDF)ERCOT-registered DG and storage application (PDF)
CenterPoint Energy
ERCOT · Houston area
Application and study-fee addendum by mail, fax, or email. Email: Residential_DG@centerpointenergy.com or Commercial_DG@centerpointenergy.comDER application package (PDF)
AEP Texas
ERCOT · South and West Texas
Follow AEP Texas’s DER interconnection process before installing. Email completed applications to der_aeptexas@aep.comDER interconnectionApplication form (PDF)
TNMP (Texas-New Mexico Power)
ERCOT · Parts of North-Central, Gulf Coast, and West Texas
We could not confirm a dedicated interconnection page. Contact TNMP; distribution interconnection follows PUCT rules 25.211 and 25.212.TNMP website (company home page)
El Paso Electric
Western grid (WECC) · El Paso area
Texas process for facilities up to 10 MW, with technical requirements and inspection before energizing.Texas interconnection up to 10 MW
Entergy Texas
MISO · Southeast Texas
Application package, interconnection agreement, W-9, and one-line diagram; utility-approved outside disconnect required. Large projects go through the MISO queue.Net metering and interconnectionMISO queue (below)
Xcel Energy (SPS)
SPP · Panhandle and South Plains
Large generators interconnect to the SPS transmission system through SPP’s queue; Xcel publishes separate guidelines for transmission-connected generation over 20 MW. We could not confirm a dedicated small-system page.Xcel Energy (company home page)SPP queue (below)
SWEPCO
SPP · Northeast Texas
Large projects go through SPP’s queue. We could not confirm a dedicated small-system page.SWEPCO (company home page)SPP queue (below)
City utilities and electric co-ops
Varies · Throughout Texas
Municipal utilities (for example Austin Energy and CPS Energy) and electric cooperatives set their own interconnection rules. Contact the utility named on the electric bill.

Transmission-level projects in ERCOT: file a generation interconnection request with ERCOT (see ERCOT below) and sign an interconnection agreement with the transmission owner. PUCT Rule 25.195 sets how much of the connection cost the transmission owner covers.

Grid operators and regions

ERCOTSPPMISOPJMCAISONYISOISO New EnglandSoutheast bilateral (utility OATT)Western utilities (OATT; WEIM/EDAM)TVAIsolated system

ERCOT

Checked against live sources 2026-09-25 · States: Texas

  1. Applies to generation adding 10 MW or more at the point of interconnection (Planning Guide 5.1.1); under 10 MW goes through the TDSP distributed generation process, with an ERCOT INR still required for registration
  2. Submit the Generation Interconnection or Change Request (GINR) in RIOO-IS and pay the fees in the current ERCOT Fee Schedule (the interconnection and full-study fees were restructured in 2023 under NPRR1153, so older $5,000/$7,000 figures are out of date); ERCOT confirms completeness within 10 business days
  3. ERCOT Security Screening Study: up to 90 days, typically ~45
  4. Within 180 days of screening results, elect to proceed to the Full Interconnection Study (FIS) or the GINR is cancelled and you start over with a new fee
  5. FIS run by the host TSP (kick-off meeting within 10 business days of your election): steady-state N-1/N-2, dynamics, short circuit, reactive capability, and sub-synchronous resonance where flagged; 40–300 days depending on POI
  6. ERCOT accepts the FIS (10–15 days); within 180 days execute the Standard Generation Interconnection Agreement (SGIA) with the TSP or the GINR is cancelled. All SGIAs signed on or after Jan 1, 2026 use the Nov 6, 2025 form approved in PUCT Project 58211
  7. Cost shift for SGIAs executed after Dec 31, 2025: under PUCT Rule 25.195 the TSP funds transmission interconnection facilities only up to a CPI-indexed allowance ($14.408 million for 2026 at 138 kV and below; above 138 kV the rule set an initial $22.5 million, also CPI-adjusted each year); the developer pays the rest. Earlier SGIAs had the TSP fund all of it, with deposits refunded at COD
  8. Registration and modeling: Resource Asset Registration Form (RARF), QSE designation, ERCOT-polled settlement meter, ICCP data link, PUCT registration for most Resource Entities
  9. Energization, synchronization, and commissioning under the ERCOT New Generator Commissioning Checklist, then commercial operations
  10. Overall expectation for ≥10 MW: roughly 18–30 months from GINR to commissioning, before equipment and construction delays (consultancy estimate, not an ERCOT commitment)

ERCOT Resource Integration pagePUCT 25.195 allowance ($14M at ≤138 kV, $22.5M above)NPRR1153 fee restructuring (PUCT approval)Batch Zero for large loads, effective July 11, 2026ERCOT Planning Guide Section 5 (current)RAPID Toolkit: Texas ERCOT interconnection (180-day rules)PUCT Rule 25.195 cost allowance for 2026

SPP

Checked against live sources 2026-09-25 · States: Arkansas, Iowa, Kansas, Louisiana, Minnesota, Missouri, Montana, Nebraska, New Mexico, North Dakota, Oklahoma, South Dakota, Texas, Wyoming

  1. SPP replaced its old DISIS cluster process with the Consolidated Planning Process (CPP), accepted by FERC and effective March 1, 2026. Transmission planning and generator interconnection now run as one cycle
  2. Annual application window, December 15 to January 15 (the transitional 2026 window ran April 1 to May 31, 2026). Applications need complete technical models, 100% site control, and financial security
  3. Annual Interconnection Cluster Study (about 180 days) with a single decision point
  4. Upfront, standardized GRID-C charges for network upgrades instead of open-ended cost allocation, then the Generator Interconnection Agreement
  5. Commissioning, model validation, and commercial operation

SPP generator interconnectionFERC order accepting SPP CPP (White & Case summary)

MISO

Checked against live sources 2026-09-25 · States: Arkansas, Illinois, Indiana, Iowa, Kentucky, Louisiana, Michigan, Minnesota, Mississippi, Missouri, Montana, North Dakota, South Dakota, Texas, Wisconsin

  1. Apply in the Definitive Planning Phase (DPP) cycle: the DPP-2026 application deadline is January 15, 2027. MISO applies regional queue caps, and some regions (East/ITC) have already hit their 2026 cap
  2. At application: non-refundable D1 fee ($7,600), D2 study deposit, M2 milestone of $8,000 per MW (cash or letter of credit), and M1 technical data. Site control is due at least 90 days before DPP Phase I kick-off
  3. DPP Phase I, II, and III system impact studies with decision points between phases; penalty-free withdrawal only if upgrade costs rise past set thresholds, otherwise part of M2 is at risk
  4. Generator Interconnection Agreement tendered and executed with MISO and the transmission owner, with further milestone payments
  5. Expedited Resource Addition Study (ERAS) is a separate fast path limited to projects meeting a load-serving entity reliability need

MISO generator interconnection (fees, deadline)MISO GI studies

PJM

Checked against live sources 2026-09-25 · States: Delaware, District of Columbia, Illinois, Indiana, Kentucky, Maryland, Michigan, New Jersey, North Carolina, Ohio, Pennsylvania, Virginia, West Virginia

  1. New requests go through annual Cycles under PJM Manual 14H. Cycle 1 closed April 27, 2026; the next Cycle window is announced by PJM. A separate Expedited Interconnection Track exists for qualifying projects ($15,000/MW readiness deposit plus a $500,000 study deposit, both at risk once the application is valid)
  2. Application: executed Application and Studies Agreement, site control evidence, study-ready PSS/E power-flow and dynamic models, a tiered study deposit ($75,000–$400,000 by size), and Readiness Deposit No. 1 ($4,000/MW)
  3. Phase I system impact study, then Decision Point I: withdraw or post Readiness Deposit No. 2 (a share of the Phase I network upgrade cost)
  4. Phase II system impact study and Decision Point II (PSCAD/EMT models due at DP2 for bulk power system projects), then Phase III and Decision Point III
  5. Final agreement negotiation: Generation Interconnection Agreement and construction service agreements, then interconnection facilities, model validation, and commercial operation

PJM service requests and Cycle timelinePJM Manual 14H (Cycle process)PJM Cycle 1 deadline announcement

CAISO

Checked against live sources 2026-09-25 · States: California, Nevada

  1. Cluster 16 application window: October 1 to October 15, 2026 (5:00 p.m. Pacific), through the Grid Resource Interconnection Portal. Treat October 8 as the practical deadline, since later filings may not get a chance to cure deficiencies. Distribution-level (WDAT) windows run earlier by utility
  2. Application fee $5,000 plus study and site-control deposits; site exclusivity and a technically valid model package required
  3. Intake scoring and zonal screening under the Interconnection Process Enhancements (IPE 2023 and IPE 5.0): commercial interest (including load-serving entity interest), project viability, and system need decide which requests enter the study
  4. Cluster study: system impact and facilities, with network upgrade allocation; Generator Interconnection Agreement and financial security postings
  5. Deliverability allocation (Full Capacity Deliverability Status is needed to sell Resource Adequacy) and New Resource Implementation to COD

CAISO interconnection request and studyCluster 16 window and October 8 cure date

NYISO

Checked against live sources 2026-09-25 · States: New York

  1. The old Class Year process has been replaced by a cluster study under FERC Order 2023 (transition cluster began August 1, 2024). An optional, rolling pre-application process is available
  2. Next cluster (the 2026 Cluster): NYISO announces the window date; the window is expected to be about 45 days. Application fee plus a study deposit scaled to project size, site control, and a physical-infeasibility screen
  3. Phase 1 cluster study, then Phase 2 including deliverability, with decision points and additional deposits
  4. Interconnection agreement with NYISO and the connecting transmission owner, security postings
  5. Commissioning, market registration, and commercial operation; ORES siting runs in parallel for projects of 25 MW or more

NYISO interconnectionsNYISO cluster study transition

ISO New England

Checked against live sources 2026-09-25 · States: Connecticut, Maine, Massachusetts, New Hampshire, Rhode Island, Vermont

  1. First full cluster request window: October 5 to November 19, 2026. Requests are accepted only during a window
  2. Complete request package with site control and financial requirements; ISO validates the request, then a customer engagement window and cluster study scoping meeting follow
  3. Cluster study of all requests together (thermal, voltage, stability, short circuit), with withdrawal penalties; some clusters are enabled by a Cluster Enabling Transmission Upgrade (CETU)
  4. Interconnection agreement with ISO New England and the transmission owner
  5. Capacity market qualification (the market is moving to a prompt/seasonal design) and commercial operation

ISO-NE interconnection process guideISO-NE cluster window notice (Sept 2026)

Southeast bilateral (utility OATT)

From our notes; not yet checked against live sources. Confirm with the operator or utility. · States: Alabama, Florida, Georgia, Mississippi, North Carolina, South Carolina

  1. Interconnection request to the serving utility under its FERC-jurisdictional OATT (LGIP or SGIP), filed via OASIS
  2. Cluster or serial study per the utility’s Order 2023 procedures: system impact, then facilities
  3. Interconnection agreement (LGIA/SGIA) with security postings
  4. Transmission service request if the offtaker is elsewhere
  5. Commissioning and commercial operation; state PSC certificate may run in parallel

Start here (ferc.gov)

Western utilities (OATT; WEIM/EDAM)

From our notes; not yet checked against live sources. Confirm with the operator or utility. · States: Arizona, California, Colorado, Idaho, Montana, Nevada, New Mexico, Oregon, Texas, Utah, Washington, Wyoming

  1. Interconnection request to the transmission provider under its OATT LGIP/SGIP via OASIS
  2. Cluster study under Order 2023 procedures with deposits and site control
  3. Facilities study and upgrade cost allocation
  4. Interconnection agreement and security
  5. Market participation through the Western Energy Imbalance Market or Extended Day-Ahead Market where the utility participates

Start here (westerneim.com)

TVA

From our notes; not yet checked against live sources. Confirm with the operator or utility. · States: Kentucky, Tennessee

  1. Interconnection request under TVA’s generator interconnection procedures
  2. Feasibility and system impact studies
  3. Facilities study and upgrade cost estimate
  4. Interconnection agreement with TVA, plus a power purchase or transmission service arrangement
  5. Commissioning and commercial operation

Start here (tva.com)

Isolated system

From our notes; not yet checked against live sources. Confirm with the operator or utility. · States: Alaska, Hawaii

  1. Interconnection request to the island or regional utility under its tariff
  2. Interconnection requirements study (hosting capacity, stability)
  3. Interconnection agreement and utility-built facilities
  4. Commissioning and commercial operation

Start here (hawaiianelectric.com)

Check before you file. Queue rules, fees, and windows change often. Confirm on the operator's or utility's site. This page is general information, not legal or engineering advice. Found an error? Let us know.