Robertson County, Texas: solar, wind, and storage permits
Who to call and what to check for a solar, wind, or battery storage project in Robertson County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.
Who handles property records and taxes in Robertson County?
The Robertson County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.
Robertson County directory (Texas Comptroller)Lease rates and rollback taxes
Which TCEQ office covers Robertson County?
TCEQ Region 9, Waco
6801 Sanger Ave, Ste 2500, Waco TX 76710-7826
Main line: 254-751-0335 · Spills, 24 hours: 800-832-8224
Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.
TCEQ region directoryConstruction stormwater permit
Does Robertson County have zoning or a solar permit?
Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.
What energy projects are proposed in Robertson County?
ERCOT's August 2026 interconnection report lists 20 proposed energy projects in Robertson County (4 solar and 16 battery storage), about 3,889 MW in all. 6 of the 20 have a signed interconnection agreement.
Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.
Scroll the table sideways to see every column.
| Project and connection point | Developer | Type | MW | Projected in service | Stage |
|---|---|---|---|---|---|
| Barton Branch IATap 345kV 3400 Twin Oak - 39950 TNP One | Barton Branch IA LLC | Battery storage (stand-alone) | 203.6 | Oct 2026 | Signed; security posted |
| Tidwell Prairie II BattTap 345kV 3400 Twin Oak - 39950 TNP One | Tidwell Prairie IIA LLC | Battery storage (stand-alone) | 203.6 | Oct 2026 | Signed; security posted |
| Bee Branch IATap TNP ONE 39950 and Twin Oak 3400 | Bee Branch IA LLCBee Branch IA LLC | Battery storage (stand-alone) | 203.8 | Jun 2027 | Signed; security posted |
| Big Rooter West Solar39950# TNTNP_ONE_3 345 KV | Big Rooter West, LLC | Solar | 403.2 | May 2028 | Signed Feb 2025 |
| Big Rooter East Solar39950 TNP One Plant 345 kV | Big Rooter East, LLC | Solar | 554.7 | May 2029 | Signed Jun 2025 |
| Big Rooter East Storage39950 TNP One Plant 345 kV | Big Rooter East, LLC | Battery storage (paired with solar) | 201.0 | Dec 2029 | Signed Jun 2025 |
| Stegall SolarElliott (Bus #53) to Franklin (Bus #57) 69kV Transmission Line | BT Martin Solar, LLC | Solar | 81.6 | May 2027 | In study |
| Stegall StorageTap connection to a new switching station on the Elliott (Bus #53)... | BT Martin Solar, LLC | Battery storage (paired with solar) | 50.5 | May 2027 | In study |
| BRP Mekong BESSTap 345 kV line from Twin Oak Switch (#3400) to TPN One Plant Switc... | BRP Mekong BESS LLC | Battery storage (stand-alone) | 409.9 | Dec 2027 | In study |
| Pioneer Path Energy Storage 1Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2 | Tempus Power management LLC | Battery storage (stand-alone) | 102.1 | Dec 2027 | In study |
| Pioneer Path Energy Storage 2Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2 | Tempus Power management LLC | Battery storage (stand-alone) | 102.1 | Dec 2027 | In study |
| Pioneer Path Energy Storage 3Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2 | Tempus Power management LLC | Battery storage (stand-alone) | 102.1 | Dec 2027 | In study |
| Pioneer Path Energy Storage 4Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2 | Tempus Power management LLC | Battery storage (stand-alone) | 102.1 | Dec 2027 | In study |
| Prairie Horizon Energy Storage 1Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2 | Tempus Power management LLC | Battery storage (stand-alone) | 102.1 | Dec 2027 | In study |
| Prairie Horizon Energy Storage 2Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2 | Tempus Power management LLC | Battery storage (stand-alone) | 102.1 | Dec 2027 | In study |
| Prairie Horizon Energy Storage 3Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2 | Tempus Power management LLC | Battery storage (stand-alone) | 102.1 | Dec 2027 | In study |
| Prairie Horizon Energy Storage 4Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2 | Tempus Power management LLC | Battery storage (stand-alone) | 102.1 | Dec 2027 | In study |
| Buffalo Meadow SolarTap Jack Creek (975) - Twin Oak (3400) 345kV line | Buffalo Meadow Energy Center, LLC | Solar | 251.3 | Sep 2028 | In study |
| Buffalo Prairie StorageTap 345kV 975 Jack Creek - 3400 Twin Oak | Buffalo Meadow Energy Center, LLC | Battery storage (paired with solar) | 308.0 | Sep 2028 | In study |
| Big Rooter West Storage39950# TNTNP_ONE_3 345 KV | Big Rooter West, LLC | Battery storage (paired with solar) | 201.1 | Dec 2028 | In study |
Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.
Where are the flood maps for Robertson County?
FEMA flood maps for Robertson County
How does a project here connect to the grid?
Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.
Interconnection by market and utilityERCOT resource integration
What state and federal reviews can apply?
Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.
Statewide and federal contactsTexas decommissioning law
Check a specific property in Robertson County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.