Lampasas County, Texas: solar, wind, and storage permits

Contacts checked 2026-09-26 · From official state and federal directories

Who to call and what to check for a solar, wind, or battery storage project in Lampasas County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.

Who handles property records and taxes in Lampasas County?

The Lampasas County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.

Lampasas County directory (Texas Comptroller)Lease rates and rollback taxes

Which TCEQ office covers Lampasas County?

TCEQ Region 9, Waco
6801 Sanger Ave, Ste 2500, Waco TX 76710-7826
Main line: 254-751-0335 · Spills, 24 hours: 800-832-8224

Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.

TCEQ region directoryConstruction stormwater permit

Does Lampasas County have zoning or a solar permit?

Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.

What energy projects are proposed in Lampasas County?

ERCOT's August 2026 interconnection report lists 10 proposed energy projects in Lampasas County (5 solar and 5 battery storage), about 1,742 MW in all. 2 of the 10 have a signed interconnection agreement.

Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.

Scroll the table sideways to see every column.

Project and connection pointDeveloperTypeMWProjected in serviceStage
Seven Springs SolarTap 7061 COPPERAS COVE 7260 Kempner 138kVHancock Springs, LLCSolar145.0May 2028Signed; security posted
Thomas Cameron BESSTap 345kV 3424 BUCKHORN SWITCH - 3422 KILLEEN SWITCHThomas Cameron BESS LLCBattery storage (stand-alone)205.5Apr 2029Signed; security posted
GIBSON BRANCH BESS7064 Lampasas Substation 138kVGibson Branch BESS LLCBattery storage (stand-alone)142.9Jan 2028In study
Hana Springs BESS7064 LAMPASAS 138KVBlack Mountain Energy Storage II LLCBattery storage (stand-alone)100.8May 2028In study
Triple B Solar Alt#2Tap 138kV 7066 Adamsville - 7064 LampasasTriple B Solar LLCSolar150.0Jul 2028In study
Aurora Energy StorageTap 345kV --- KILL_SS_5 (3422) --- BUCK_H_5 (3424)Aurora Energy Storage, LLCBattery storage (stand-alone)306.2Sep 2028In study
Senterfitt SolarTap 138 kV 7080 Lometa - 7064 LampasasAETS Development Holdings LLCSolar68.4Jul 2029In study
Solgen Solar7066 Adamsville 138kVLampasas Hybrid Energy LLCSolar160.2Aug 2029In study
Solgen Storage7066 Adamsville 138kVLampasas Hybrid Energy LLCBattery storage (paired with solar)150.3Aug 2029In study
Barkley Creek SolarTap 345 kV Line from Russel Gap Switch (Bus# 3348) - Killeen Switch...174 Power Global Properties, LLCSolar312.4Oct 2029In study

Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.

Where are the flood maps for Lampasas County?

FEMA flood maps for Lampasas County

How does a project here connect to the grid?

Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.

Interconnection by market and utilityERCOT resource integration

What state and federal reviews can apply?

Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.

Statewide and federal contactsTexas decommissioning law

Check a specific property in Lampasas County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Open Quicksand Check

Other counties served by TCEQ Region 9

Bell · Bosque · Brazos · Burleson · Coryell · Falls · Freestone · Grimes · Hamilton · Hill · Leon · Limestone · Madison · McLennan · Milam · Mills · Robertson · San Saba · Washington

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not legal advice. Found an error? Let us know.