Bell County, Texas: solar, wind, and storage permits

Contacts checked 2026-09-26 · From official state and federal directories

Who to call and what to check for a solar, wind, or battery storage project in Bell County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.

Who handles property records and taxes in Bell County?

The Bell County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.

Bell County directory (Texas Comptroller)Lease rates and rollback taxes

Which TCEQ office covers Bell County?

TCEQ Region 9, Waco
6801 Sanger Ave, Ste 2500, Waco TX 76710-7826
Main line: 254-751-0335 · Spills, 24 hours: 800-832-8224

Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.

TCEQ region directoryConstruction stormwater permit

Does Bell County have zoning or a solar permit?

Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.

What energy projects are proposed in Bell County?

ERCOT's August 2026 interconnection report lists 13 proposed energy projects in Bell County (5 solar, 7 battery storage and 1 gas), about 3,098 MW in all. 8 of the 13 have a signed interconnection agreement, and 4 have been energized or approved to connect.

Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.

Scroll the table sideways to see every column.

Project and connection pointDeveloperTypeMWProjected in serviceStage
Hermes SolarTap 345kV 3687 Bell County East Switch - 39950 TNP One Plant Ckt 2Bell 1 Solar, LLCSolar100.4Jun 2026Approved to connect
Hermes StorageTap 345kV 3687 Bell County East Switch - 39950 TNP One Plant Ckt 2Bell 1 Storage LLCBattery storage100.4Aug 2026Approved to connect
Chillingham Solar3687 Bell County East 345kVChillingham Solar LLCSolar352.4Oct 2026Approved to connect
Limewood Solar3420 Temple Pecan Creek 138kVLimewood Bell Renewables, LLCSolar204.6Dec 2026Energized
Cosper SolarTap 138kV 115 Ding Dong - 3630 Copperas Cove TuGransolar Texas Twenty LLCSolar148.2Nov 2027Signed; security posted
Big Elm Storage3404 Belfalls 345kVBig Elm Storage, LLCBattery storage (paired with solar)120.0Dec 2028Signed; security posted
Limewood Storage3420 Temple Pecan Creek 138kVLimewood Bell Renewables LLCBattery storage (paired with solar)50.0Dec 2028Signed; security posted
Goldeneye BESS3423 KILLEEN Switch 138 KVBlack Mountain Energy Storage IIBattery storage (stand-alone)201.6May 2028Signed Feb 2024
Lavita BESSTap 345kV Temple Pecan Creek (3412) - Temple Switch (3414) 345kV ckt 2Lavita BESS, LLCBattery storage (stand-alone)606.0Jul 2028In study
Butcherbird SolarTap 138 kV - Bell County #133 to Bartlett Switch #114Butcherbird Solar, LLCSolar116.0Jan 2029In study
Bell County Leifester StorageTap 138kV 3428 Killeen South – 13628 Founders Trail SubDM-BCRCML, LLCBattery storage (stand-alone)204.8Sep 2029In study
Bell County Morgan StorageTo Tap 138 kV Trimmier Substation (Bus# 136)DM-BCTRM, LLCBattery storage (stand-alone)256.3Dec 2029In study
Riviera GasTap #3414 Temple Switch - #3780 Tower Switch 345kV DCKT LineBKV-BPP PowerGas combined cycle636.9Jun 2030In study

Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.

Where are the flood maps for Bell County?

FEMA flood maps for Bell County

How does a project here connect to the grid?

Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.

Interconnection by market and utilityERCOT resource integration

What state and federal reviews can apply?

Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.

Statewide and federal contactsTexas decommissioning law

Check a specific property in Bell County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Open Quicksand Check

Other counties served by TCEQ Region 9

Bosque · Brazos · Burleson · Coryell · Falls · Freestone · Grimes · Hamilton · Hill · Lampasas · Leon · Limestone · Madison · McLennan · Milam · Mills · Robertson · San Saba · Washington

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not legal advice. Found an error? Let us know.