Quicksand Check

Home › Texas permits › Pecos County

Pecos County, Texas: solar, wind, and storage permits

Contacts checked 2026-09-26 · From official state and federal directories

Who to call and what to check for a solar, wind, or battery storage project in Pecos County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.

Who handles property records and taxes in Pecos County?

The Pecos County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.

Pecos County directory (Texas Comptroller)Lease rates and rollback taxes

Which TCEQ office covers Pecos County?

TCEQ Region 7, Midland
10 Desta Dr, Ste 350E, Midland TX 79705-4530
Main line: 432-570-1359 · Spills, 24 hours: 800-832-8224

Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.

TCEQ region directoryConstruction stormwater permit

Does Pecos County have zoning or a solar permit?

Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.

What energy projects are proposed in Pecos County?

ERCOT's August 2026 interconnection report lists 56 proposed energy projects in Pecos County (21 solar, 13 wind, 15 battery storage and 7 gas), about 20,717 MW in all. 18 of the 56 have a signed interconnection agreement, and 6 have been energized or approved to connect.

Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.

Scroll the table sideways to see every column.

Project and connection pointDeveloperTypeMWProjected in serviceStage
Desert Sky repowertwo LCRA 138kVDESERT SKY WIND FARM LLCWind7.2May 2023Approved to connect
Sherbino II Wind repower38430 TN White Baker 138kVSherbino II Wind Farm LLCWind-18.0Aug 2026Approved to connect
Hovey Solar 260385 Solstice 138 kVBARILLA SOLAR, LLCSolar8.1Sep 2026Approved to connect
Indian Mesa repower76019 Indian NWP 138kVNexteraWind9.3Dec 2026Approved to connect
Woodward 2 repower60400 Lynx 138kVNexteraWindSelf-limitingDec 2026Approved to connect
Woodward I repower60400 Lynx 138kVNexteraWindSelf-limitingDec 2026Approved to connect
Longfellow BESS I38432 TNCENTRY1_1 138 KVCENTURY GAS PROCESSING, LLCBattery storage (paired with solar)55.0Nov 2026Signed; security posted
Longfellow BESS II38432 TNCENTRY2_1 138 KVCENTURY GAS PROCESSING, LLCBattery storage (paired with solar)105.8Nov 2026Signed; security posted
Alamo Street BESS2TSP Station Name: Alamo Street Sub TNPMomentum Pilsner, LLCBattery storage (stand-alone)10.0Mar 2027Signed; security posted
Sherbino II BESS SLF38430 TNMP White baker Switching Station 138kVPhoenix Battery Storage, LLCBattery storage (paired with wind)77.4Apr 2027Signed; security posted
Laurel Wind Energy CenterTap Solstice to Bakersfield (Bus# 60404 -76002) 345kV Ckt 2 andLAUREL ENERGY CENTER, LLCWind306.6Dec 2027Signed; security posted
Skyrider Wind138kV #38365 TNPINIONNextEra Energy Interconnection Holdings, LLCWind370.0Jul 2028Signed; security posted
Selenite Springs SolarTap 138kV 38355 Leon Creek Switching Station - 38308 Woodhouse Swit...Selenite Springs Solar, LLCSolar253.0Aug 2028Signed; security posted
Springfield SolarTap Leon Creek (#38355) to Woodhouse Station (#38308) 138kV lineBOULEVARD ASSOCIATES, LLCSolar400.0Aug 2028Signed; security posted
Big Canyon Wind38441 Bottlebrush 345kVLongfellow Wind, LLCWind1,500.0Jul 2030Signed; security posted
Pecos WindTap 345 kV 60404 Solstice (SOLSTICE7A) – 76002 Bakersfield (L_BAKER...Midnight Energy Center, LLCWind193.8May 2028Signed Mar 2026
Longfellow Solar I38431 TNCENTRY1_1 138 KVCENTURY GAS PROCESSING, LLCSolar178.2Dec 2028Signed Apr 2025
Longfellow Solar II38432 TNCENTRY2_1 138 KVCENTURY GAS PROCESSING, LLCSolar207.4Dec 2028Signed Apr 2025
Larrea SolarTap 345kV 76002 Bakerfield - 60404 Solstice CKT#1Greasewood IV LLCSolar231.6Sep 2027In study
Grand Mesa BESS76582 MESA VIEW SWITCH 138kVPERRY GREEN POWER LLCBattery storage (stand-alone)253.3Sep 2027In study
Wisdom BESS SLFTap 138 kV #38455 HOLIDAY SUB TNP - 138 kV #38450 SOAPTREE TNPWisdom Green Energy LLCBattery storage (paired with solar)102.9Oct 2027In study
Wisdom Solar SLFTap 138 kV #38455 HOLIDAY SUB TNP - #38450 SOAPTREE TNPWisdom Green Energy LLCSolar299.4Oct 2027In study
Rock House Draw Gas38431 TNCENTRY1_1 138 KVLongfellow Power LLCGas engines523.0Nov 2027In study
Comanche Creek generating stationTNCENTRY1_1 [138 kV] ( 38431)Longfellow Power LLCGas engines107.0Dec 2027In study
Mensa BESS60718 Pecos Valley 138kVBRP Mensa BESS LLCBattery storage (stand-alone)309.0Jun 2028In study
st gall IIIA Storage38355 LEON_CRK 138kVTempus Power Management LLCBattery storage (stand-alone)200.7Jun 2028In study
st gall IIIB Storage38355 LEON_CRK 138kVTempus Power Management LLCBattery storage (stand-alone)200.7Jun 2028In study
Pecos Flats Solar IITap 345 kV 60404 SOLSTICE - 11098 SANDLAKE_5Glass Mountain Solar, LLCSolar301.5Feb 2029In study
Pecos Flats Solar IIITap 345 kV 60404 SOLSTICE - 11098 SANDLAKE_5Glass Mountain Solar, LLCSolar301.5Feb 2029In study
Glass Mountain BB Solar 1Tap 345kV 60404 Solstice to 38441 BottlebrushGlass Mountain Solar, LLCSolar302.7Mar 2029In study
Glass Mountain BB Solar 2Tap 345kV 60404 Solstice to 38441 BottlebrushGlass Mountain Solar II, LLCSolar302.7Mar 2029In study
Ashtrom Marigold BESS SLF860 GIRVINSW 345kVMarigold BESS LLCBattery storage (stand-alone)153.9Apr 2029In study
Tierra Bonita BESS SLF860 GIRVINSW 345kVGreasewood II BESS LLCBattery storage (stand-alone)Self-limitingJun 2029In study
Star Of Texas Solar60152 Fort Stockton Switch 345kVBOULEVARD ASSOCIATES, LLCSolar415.0Jul 2029In study
Glass Mountain BB Solar 3Tap 345kV 60404 Solstice to 38441 BottlebrushGlass Mountain Solar III, LLCSolar302.6Oct 2029In study
Glass Mountain BB Solar 4Tap 345kV 60404 Solstice to 38441 BottlebrushGlass Mountain Solar IV, LLCSolar302.6Oct 2029In study
Glass Mountain BB Solar 5Tap 345kV 60404 Solstice to 38441 BottlebrushGlass Mountain Solar V, LLCSolar302.6Oct 2029In study
Pecos Flats Solar60404 SOLSTICE 345 kVGlass Mountain Solar, LLCSolar302.4Oct 2029In study
BRP Octans BESS6671 Tombstone 138kVBRP OCTANS BESS LLCBattery storage (stand-alone)129.6Dec 2029In study
The Giant Arc IBus #60404 SOLSTICE CKT 01Powering Knowledge, LLCGas engines1,300.0Apr 2030In study
The Giant Arc-IIBus #60404 SOLSTICE CKT 02Powering Knowledge, LLCGas engines1,300.0Apr 2030In study
Pecos Flats Wind ITap Bottlebrush (38441) to White Baker (38435) 345kV Line (TNMP)Pecos Flats Wind, LLCWind506.9Jun 2030In study
Pecos Flats Wind IITap 345kV 38441 Bottlebrush to 38435 White Baker 345kV line (TNMP)Pecos Flats Wind II, LLCWind507.9Jun 2030In study
Gravitas I Natural GasTap 345kV Solstice (60404) - Bakersfield (76002) Double circuit lineS&S Renewables, LLCGas engines1,247.0Jun 2030In study
Gravitas I SolarTap 345kV Solstice (60404) - Bakersfield (76002) Double circuit lineS&S Renewables, LLCSolar1,124.8Jun 2030In study
Gravitas I WindTap 345kV Solstice (60404) - Bakersfield (76002) Double circuit lineS&S Renewables, LLCWind636.5Jun 2030In study
Pentarise BESS138 kV Pig Creek (#60393)Pentarise BESS, LLCBattery storage (stand-alone)150.6Jun 2030In study
Permian I Natural GasTap TNMP White Baker (38435)–Bottlebrush(38441) 345-kV double-circuitS&S Renewables, LLCGas engines1,247.0Jun 2030In study
Permian I SolarTap TNMP White Baker (38435)–Bottlebrush(38441) 345-kV double-circuitS&S Renewables, LLCSolar1,125.7Jun 2030In study
Permian I WindTap TNMP White Baker (38435)–Bottlebrush(38441) 345-kV double-circuitS&S Renewables, LLCWind636.5Jun 2030In study
Elk Ridge SolarAEP Solstice Substation #60404Boulevard Associates, LLCSolar503.0Jul 2030In study
MRR SolarSolstice Substation #60384 -AEPBOULEVARD ASSOCIATES, LLCSolar500.0Jul 2030In study
Rio Vista SolarTap 138kV #60393 PigCreek4A – #60385 Solstice4ARio Vista Solar, LLCSolar553.7Sep 2030In study
Rio Vista StorageTap 138kV #60393 Pigcreek4A – #60385 Solstice4ARio Vista Storage, LLCBattery storage (paired with solar)103.4Sep 2030In study
Gatsby Energy StorageFort Lancaster 138 kV Substation (PSSE Bus #76579)Gatsby Energy Storage LLCBattery storage (stand-alone)103.4Dec 2030In study
Valentine Energy Center60400 Lynx 138kVValentine Energy Center, LLCGas engines162.3Feb 2031In study

Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.

Where are the flood maps for Pecos County?

FEMA flood maps for Pecos County

How does a project here connect to the grid?

Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.

Interconnection by market and utilityERCOT resource integration

What state and federal reviews can apply?

Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.

Statewide and federal contactsTexas decommissioning law

Check a specific property in Pecos County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Open Quicksand Check

Other counties served by TCEQ Region 7

Andrews · Borden · Crane · Dawson · Ector · Gaines · Glasscock · Howard · Loving · Martin · Midland · Reeves · Terrell · Upton · Ward · Winkler

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not legal advice. Found an error? Let us know.