Ector County, Texas: solar, wind, and storage permits

Contacts checked 2026-09-26 · From official state and federal directories

Who to call and what to check for a solar, wind, or battery storage project in Ector County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.

Who handles property records and taxes in Ector County?

The Ector County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.

Ector County directory (Texas Comptroller)Lease rates and rollback taxes

Which TCEQ office covers Ector County?

TCEQ Region 7, Midland
10 Desta Dr, Ste 350E, Midland TX 79705-4530
Main line: 432-570-1359 · Spills, 24 hours: 800-832-8224

Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.

TCEQ region directoryConstruction stormwater permit

Does Ector County have zoning or a solar permit?

Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.

What energy projects are proposed in Ector County?

ERCOT's August 2026 interconnection report lists 22 proposed energy projects in Ector County (11 solar, 10 battery storage and 1 gas), about 4,178 MW in all. 5 of the 22 have a signed interconnection agreement, and 2 have been energized or approved to connect.

Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.

Scroll the table sideways to see every column.

Project and connection pointDeveloperTypeMWProjected in serviceStage
Greyhound SolarTap 345kV 11010 Wolf - 1018 MossRockhound Solar 2, LLC dba "Greyhound Solar"Solar335.4Jun 2026Approved to connect
Apple BESSStation Name - AppleApple Infra LLCBattery storage (stand-alone)9.9Oct 2026Energized
EMPower Odessa (TEF - Due Diligence)Tap 138 kV 1110 EDWARDS TAP - 1102 JUDKINSEMPOWER USA, LLCGas engines122.8Mar 2028Signed; security posted
Sisters Solartapping the 345 kV line connecting Moss Switch (Bus# 1018) to Wolf...Oberon Solar LLCSolar100.5Sep 2028Signed; security posted
Van Zandt Energy Storage1027 Odessa EHV Switch 138 kVRocky Mountain Energy Holdings, LLCBattery storage (stand-alone)256.0May 2027Signed Mar 2025
Momentum Hazy Jane BESSTap 138kV 1102 Judkins - 1110 EdwardMOMENTUM HAZY JANE, LLCBattery storage (stand-alone)125.5Feb 2028In study
Seragio BESS11140 ECTRCNTYN_8 138kVSeragio BESS, LLCBattery storage (stand-alone)201.1Apr 2028In study
M-Bar BESS I1141 Holt Switch Substation 138 kVM-Bar Energy I, LLCBattery storage (paired with solar)82.1Sep 2028In study
M-Bar Solar I1141 Holt Switch Substation 138kVM-Bar Energy I, LLCSolar30.2Sep 2028In study
Ophelia SolarTap 138 kV Raceway Switch #18663 - Shin Oak POD #11128Ophelia SolarSolar110.5Sep 2028In study
Sisters Solar - Phase 210009 McGee 345 kVOberon Solar IV, LLCSolar201.5Sep 2028In study
Sisters Solar IItap 345kV 11010 Wolf Switching Station - 10012 MeteorOberon Solar III, LLCSolar205.5Dec 2028In study
GPlains SolarTap 138kV #1013 WOLFSS_8 - #1103 SANDHLTA_8Gypsum Plains Solar, LLCSolar151.3Jun 2029In study
GPlains StorageTap 138kV WOLFSS_8 (1013) - SANDHLTA_8 (1103)Gypsum Plains Solar, LLCBattery storage (paired with solar)51.3Jun 2029In study
Gypsum Plains SolarTap 345kv line Wolf BUS# 11010 - Reiter BUS#18544Gypsum Plains Solar, LLCSolar503.1Jun 2029In study
Gypsum Plains StorageTap 345kv 11010 Wolf - 18544 ReiterGypsum Plains Solar, LLCBattery storage (paired with solar)211.1Jun 2029In study
Firebird BESSTap 138kV #1099 Southwestern Portland Tap - #1052 RexallTX BESS 6, LLCBattery storage (stand-alone)102.7Jun 2029In study
Velociraptor BESS I10012 METEOR_5 Substation 345kVVelociraptor BESS I, LLCBattery storage (paired with solar)246.0Dec 2029In study
Velociraptor BESS IITap Wolf (#11010) - Reiter Switch (#18544) Ckt1 345KVVelociraptor BESS II, LLCBattery storage (paired with solar)246.1Dec 2029In study
Velociraptor Solar I#10012 METEOR 5 Substation 345kVVelociraptor Solar I, LLCSolar241.7Dec 2029In study
Velociraptor Solar IITap Wolf (#11010) - Reiter Switch (#18544) Ckt1 345KVVelociraptor Solar II, LLCSolar241.8Dec 2029In study
Jackrabbit Flats SolarTap 345 kV 1185 Midland County NW - 1018 MossJackrabbit Flats Solar LLCSolar401.3Jun 2030In study

Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.

Where are the flood maps for Ector County?

FEMA flood maps for Ector County

How does a project here connect to the grid?

Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.

Interconnection by market and utilityERCOT resource integration

What state and federal reviews can apply?

Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.

Statewide and federal contactsTexas decommissioning law

Check a specific property in Ector County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Open Quicksand Check

Other counties served by TCEQ Region 7

Andrews · Borden · Crane · Dawson · Gaines · Glasscock · Howard · Loving · Martin · Midland · Pecos · Reeves · Terrell · Upton · Ward · Winkler

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not legal advice. Found an error? Let us know.