Quicksand Check

Home › Texas permits › Crane County

Crane County, Texas: solar, wind, and storage permits

Contacts checked 2026-09-26 · From official state and federal directories

Who to call and what to check for a solar, wind, or battery storage project in Crane County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.

Who handles property records and taxes in Crane County?

The Crane County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.

Crane County directory (Texas Comptroller)Lease rates and rollback taxes

Which TCEQ office covers Crane County?

TCEQ Region 7, Midland
10 Desta Dr, Ste 350E, Midland TX 79705-4530
Main line: 432-570-1359 · Spills, 24 hours: 800-832-8224

Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.

TCEQ region directoryConstruction stormwater permit

Does Crane County have zoning or a solar permit?

Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.

What energy projects are proposed in Crane County?

ERCOT's August 2026 interconnection report lists 13 proposed energy projects in Crane County (5 solar and 8 battery storage), about 2,944 MW in all. 4 of the 13 have a signed interconnection agreement, and 1 has been energized or approved to connect.

Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.

Scroll the table sideways to see every column.

Project and connection pointDeveloperTypeMWProjected in serviceStage
Soda Lake BESS 1138kV Soda Lake Substation (#76026)Mendoza Trail BESS, LLCBattery storage (paired with solar)203.9Aug 2026Approved to connect
Soda Lake Solar 2 SLF138 kV Soda Lake (#76026)Crane II Solar Electric, LLCSolar201.7Oct 2028Signed Mar 2022
Tri-X Solar 1 SLF138 kV Soda Lake (#76026)Crane I Solar Electric, LLCSolar201.5Oct 2028Signed Feb 2022
Cattle Drive Solar76000 North McCamey 345kVCattle Drive Solar, LLCSolar307.0Mar 2029Signed Dec 2025
BRP Pictor BESS60400 Lynx 138kVBRP Pictor BESS LLCBattery storage (stand-alone)201.1Nov 2025In study
Fowler Ranch Storage76025 Castle Mountain 138kVCrane BESS, LLCBattery storage (stand-alone)26.1Jun 2027In study
BRP Ampato BESS10002 NS Crane Switch 138kVBRP Ampato BESS LLCBattery storage (stand-alone)121.6Dec 2027In study
Soda Lake BESS 2 SLF138 kV Soda Lake (#76026)Crane II Solar Electric, LLCBattery storage (paired with solar)205.3Oct 2028In study
Tri-X BESS 1 SLF138 kV Soda Lake (#76026)Crane I Solar Electric, LLCBattery storage (paired with solar)205.3Oct 2028In study
Western Flats SolarTap 138 kV 76615 Crane -76635 King Mountain; POI is 7.85 miles from...Hecate Energy Point Mountain Solar Facility 1 LLCSolar410.2Nov 2028In study
Western Flats StorageTap 138 kV 76615 Crane -76635 King MountainHecate Energy Point Mountain Solar Facility 1 LLCBattery storage (paired with solar)410.7Nov 2028In study
Tierra Loma SolarTap 345 kV #18668 ROCK DRAW - #76000 NORTH MCCAMEY ckt 1Tierra Loma Solar, LLCSolar250.0Sep 2029In study
Tierra Loma StorageTap 345 kV #18668 ROCK DRAW - #76000 NORTH MCCAMEY ckt 1Tierra Loma Solar, LLCBattery storage (paired with solar)200.0Sep 2029In study

Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.

Where are the flood maps for Crane County?

FEMA flood maps for Crane County

How does a project here connect to the grid?

Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.

Interconnection by market and utilityERCOT resource integration

What state and federal reviews can apply?

Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.

Statewide and federal contactsTexas decommissioning law

Check a specific property in Crane County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Open Quicksand Check

Other counties served by TCEQ Region 7

Andrews · Borden · Dawson · Ector · Gaines · Glasscock · Howard · Loving · Martin · Midland · Pecos · Reeves · Terrell · Upton · Ward · Winkler

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not legal advice. Found an error? Let us know.