Navarro County, Texas: solar, wind, and storage permits
Who to call and what to check for a solar, wind, or battery storage project in Navarro County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.
Who handles property records and taxes in Navarro County?
The Navarro County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.
Navarro County directory (Texas Comptroller)Lease rates and rollback taxes
Which TCEQ office covers Navarro County?
TCEQ Region 4, Dallas/Fort Worth
2309 Gravel Dr, Fort Worth TX 76118-6951
Main line: 817-588-5800 · Spills, 24 hours: 800-832-8224
Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.
TCEQ region directoryConstruction stormwater permit
Does Navarro County have zoning or a solar permit?
Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.
What energy projects are proposed in Navarro County?
ERCOT's August 2026 interconnection report lists 26 proposed energy projects in Navarro County (16 solar, 3 wind and 7 battery storage), about 4,255 MW in all. 11 of the 26 have a signed interconnection agreement, and 2 have been energized or approved to connect.
Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.
Scroll the table sideways to see every column.
| Project and connection point | Developer | Type | MW | Projected in service | Stage |
|---|---|---|---|---|---|
| Board Creek Wind345kV 3386 Outlaw Switch | Limestone Wind Project, LLC | Wind | 299.2 | Oct 2026 | Approved to connect |
| Armadillo Solar3387 Revolution 138kV | Armadillo Solar Center, LLC | Solar | 150.5 | Dec 2026 | Energized |
| Bluebonnet Prairie WindTap 138kV 200 CHATFIELD - 3454 MONTFTSS__8 | Bluebonnet Prairie Wind, LLC | Wind | 180.0 | Jul 2028 | Under construction |
| Yellow Cat WindTap 345kV 1906 Venus - 68091 Navarro | Yellow Cat Wind LLC | Wind | 262.0 | Mar 2027 | Signed; security posted |
| TORMES SOLARtap 345kV 1906 Venus - 68091 Navarro | BDPU SOLAR TORMES LLC | Solar | 356.6 | Mar 2027 | Signed; security posted |
| Tehuacana Creek SolarTap 345kV 3381 Big Brown – 68091 Navarro circuit | Tehuacana Creek Solar LLC | Solar | 505.4 | May 2027 | Signed; security posted |
| Elm Flats Solar SLFTap 138kV 3472 BRIAR_CRK_8 – 3467 POWELL1_8 | Orca Falls Solar, LLC | Solar | 125.8 | Sep 2027 | Signed; security posted |
| Elm Flats Storage SLFTap 138kV 3472 BRIAR_CRK_8 – 3467 POWELL1_8 | Orca Falls Solar, LLC | Battery storage (paired with solar) | Self-limiting | Sep 2027 | Signed; security posted |
| Glasgow SolarTap 345kV #2466 Big Onion - #68091 Navarro | Glasgow Solar LLC | Solar | 203.5 | Mar 2028 | Signed; security posted |
| Glasgow StorageTap 345kV #2466 Big Onion - #68091 Navarro | Glasgow Solar LLC | Battery storage (paired with solar) | 101.0 | Mar 2028 | Signed; security posted |
| Cape Rich BESS3387 Revolution Switch 138kV | Cape Rich BESS | Battery storage (stand-alone) | 150.5 | Apr 2030 | Signed Feb 2025 |
| Goodalta Solartap 138kV 3127 Trinidad - 212 Winkler | GoodAlta Power Center LLC | Solar | 221.4 | Sep 2027 | In study |
| Eytcheson Ranches SolarTap 69kV 186 Navarro Mills – 107 Prairie Hill | Gransolar Texas Fourteen, LLC | Solar | 76.4 | Jan 2028 | In study |
| Whistle SolarTap 138kV 213 Haney – 3478 Navarro | Gransolar Texas Nineteen, LLC | Solar | 56.3 | May 2028 | In study |
| Wensowitch SolarTapping 138 kV line Telico (192) to Montfort Switch (3454) | Greenalia Solar Power Wensowitch LLC | Solar | 146.1 | Sep 2028 | In study |
| Santa Monica SolarTap 345 KV 68091 NAVARRO - 3381 BIGBRNW_5 Ckt 2 | Karol Solar IV | Solar | 105.8 | Sep 2028 | In study |
| Wildflower StorageDrane switch #3295 | Wildflower Storage LLC | Battery storage (stand-alone) | 359.1 | Sep 2028 | In study |
| Hector SolarHaney (213) - Hubbard_8 (3515) 138kV Line | Hector Solar, LLC | Solar | 81.6 | Oct 2028 | In study |
| Hector StorageHaney (213) - Hubbard_8 (3515) 138kV Line | Hector Solar, LLC | Battery storage (paired with solar) | 42.7 | Oct 2028 | In study |
| Kennedy SolarTap 345kV 68040 Kopprl Capacitor Yard - 68091 Navarro | Kennedy Bypass Solar LLC | Solar | 101.5 | Dec 2028 | In study |
| Kennedy StorageTap 345kV 68040 Kopprl Capacitor Yard - 68091 Navarro | Kennedy Bypass Solar LLC | Battery storage (paired with solar) | 25.3 | Dec 2028 | In study |
| Pisgah Ridge Solar 2Tap 345kV 68091 Navarro - 46020 Limestone | Pisgah Ridge Solar 2, LLC | Solar | 101.9 | Mar 2029 | In study |
| Pisgah Ridge Storage 3Tap 345kV 68091 Navarro - 46020 Limestone | Pisgah Ridge 3, LLC | Battery storage (paired with solar) | 101.4 | Mar 2029 | In study |
| Ponferrada SolarTap 138 KV 3456 CORSWEST1_8 - 3457 CORS_MOBT_8 | Karol Solar VI | Solar | 148.9 | Apr 2029 | In study |
| Main Horn Solar3387 Revolution 138 KV | Main Horn Solar LLC | Solar | 100.4 | Sep 2029 | In study |
| Oak Valley Solar68091 (Navarro) (345) | Oak Valley Solar LLC | Solar | 251.3 | Sep 2029 | In study |
Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.
Where are the flood maps for Navarro County?
FEMA flood maps for Navarro County
How does a project here connect to the grid?
Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.
Interconnection by market and utilityERCOT resource integration
What state and federal reviews can apply?
Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.
Statewide and federal contactsTexas decommissioning law
Check a specific property in Navarro County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.