Contacts checked 2026-09-26 · From official state and federal directories

Who to call and what to check for a solar, wind, or battery storage project in Hunt County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.

Who handles property records and taxes in Hunt County?

The Hunt County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.

Hunt County directory (Texas Comptroller)Lease rates and rollback taxes

Which TCEQ office covers Hunt County?

TCEQ Region 4, Dallas/Fort Worth
2309 Gravel Dr, Fort Worth TX 76118-6951
Main line: 817-588-5800 · Spills, 24 hours: 800-832-8224

Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.

TCEQ region directoryConstruction stormwater permit

Does Hunt County have zoning or a solar permit?

Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.

What energy projects are proposed in Hunt County?

ERCOT's August 2026 interconnection report lists 10 proposed energy projects in Hunt County (3 solar, 5 battery storage and 2 gas), about 1,476 MW in all. 2 of the 10 have a signed interconnection agreement.

Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.

Scroll the table sideways to see every column.

Project and connection pointDeveloperTypeMWProjected in serviceStage
McMurtre Storagetap 138kV 1819 Commerce South - 1815 Cumby TapBT McMurtre Storage, LLCBattery storage (stand-alone)176.1Dec 2027Signed; security posted
Pink Solar SLF971 Pruitt 138kVPink Solar, LLCSolar152.4Jul 2029Signed Aug 2022
Power Lane II Gas - AlternateTap 138kV Caddo Mills Explorer (11832) – Scatter Branch Sub (1818)...GEUSGas engines104.4Jun 2027In study
Power Lane II - GasGREENV_IN_8 (977) via (future) GEUS_STM SubstationGEUSGas engines104.5Aug 2027In study
18-BRAVO BESS138 kV Commerce Switch Substation. Bus no. #1816Scout Energy Management, LLCBattery storage (stand-alone)407.0Feb 2028In study
Fermata BESSTap 345kV 2464# CASHSW_T5 – 2461# ROYSE_N5Fermata BESS, LLCBattery storage (stand-alone)204.0Jul 2028In study
MAKALU SOLARTap 138kV 977 Pruitt - 971 GreenvilleAbei Energy Green X LLCSolar50.2Jul 2028In study
Ceres BESSTap 138 kV 6883 QUINLAN NORTH SS - 6860 UNION VALLEY SSCeres BESS, LLCBattery storage (stand-alone)202.7Aug 2028In study
VALDIVIAN SOLAR138kV 1816 Commerce Switch - 1809 Wolf CityAbei Energy Green III LLCSolar74.9Sep 2028In study
Pink Storage SLF971 Pruitt 138kVPink Solar, LLCBattery storage (paired with solar)Self-limitingJul 2029In study

Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.

Where are the flood maps for Hunt County?

FEMA flood maps for Hunt County

How does a project here connect to the grid?

Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.

Interconnection by market and utilityERCOT resource integration

What state and federal reviews can apply?

Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.

Statewide and federal contactsTexas decommissioning law

Check a specific property in Hunt County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Open Quicksand Check

Other counties served by TCEQ Region 4

Collin · Cooke · Dallas · Denton · Ellis · Erath · Fannin · Grayson · Hood · Johnson · Kaufman · Navarro · Palo Pinto · Parker · Rockwall · Somervell · Tarrant · Wise

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not legal advice. Found an error? Let us know.