Home › Texas permits › Dallas County
Dallas County, Texas: solar, wind, and storage permits
Who to call and what to check for a solar, wind, or battery storage project in Dallas County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.
Who handles property records and taxes in Dallas County?
The Dallas County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.
Dallas County directory (Texas Comptroller)Lease rates and rollback taxes
Which TCEQ office covers Dallas County?
TCEQ Region 4, Dallas/Fort Worth
2309 Gravel Dr, Fort Worth TX 76118-6951
Main line: 817-588-5800 · Spills, 24 hours: 800-832-8224
Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.
TCEQ region directoryConstruction stormwater permit
Does Dallas County have zoning or a solar permit?
Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.
What energy projects are proposed in Dallas County?
ERCOT's August 2026 interconnection report lists 9 proposed energy projects in Dallas County (8 battery storage and 1 other), about 867 MW in all. None has a signed interconnection agreement yet.
Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.
Scroll the table sideways to see every column.
| Project and connection point | Developer | Type | MW | Projected in service | Stage |
|---|---|---|---|---|---|
| Atlanta TxHSR TPSS DS-1tap 138kV 2429 Watermill E - 3083 Wilmer | Texas Central Rail Holdings, LLC | Other | 50.0 | Jul 2028 | In study |
| watermelon 1 energy storageTap on 2427 WATMLL_W5 345.00 - 2432 TRICRN1_5 345.00 345kV line... | Tempus power management LLC | Battery storage (stand-alone) | 102.1 | Mar 2029 | In study |
| watermelon 2 energy storageTap on 2427 WATMLL_W5 345.00 - 2432 TRICRN1_5 345.00 345kV line ckt 1. | Tempus power management LLC | Battery storage (stand-alone) | 102.1 | Mar 2029 | In study |
| watermelon 3 energy storageTap on 2427 WATMLL_W5 345.00 - 2432 TRICRN1_5 345.00 345kV line ckt... | Tempus power management LLC | Battery storage (stand-alone) | 102.1 | Mar 2029 | In study |
| watermelon 4 energy storageTap on 2427 WATMLL_W5 345.00 - 2432 TRICRN1_5 345.00 345kV line ckt 1. | Tempus power management LLC | Battery storage (stand-alone) | 102.1 | Mar 2029 | In study |
| watermelon 5 energy storageTap on 2427 WATMLL_W5 345.00 - 2432 TRICRN1_5 345.00 345kV line ckt 1. | Tempus power management LLC | Battery storage (stand-alone) | 102.1 | Mar 2029 | In study |
| watermelon 6 energy storageTap on 2427 WATMLL_W5 345.00 - 2432 TRICRN1_5 345.00 345kV line ckt 1. | Tempus power management LLC | Battery storage (stand-alone) | 102.1 | Mar 2029 | In study |
| watermelon 7 energy storageTap on 2427 WATMLL_W5 345.00 - 2432 TRICRN1_5 345.00 345kV line ckt 1. | Tempus power management LLC | Battery storage (stand-alone) | 102.1 | Mar 2029 | In study |
| watermelon 8 energy storageTap on 2427 WATMLL_W5 345.00 - 2432 TRICRN1_5 345.00 345kV line ckt 1. | Tempus power management LLC | Battery storage (stand-alone) | 102.1 | Mar 2029 | In study |
Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.
Where are the flood maps for Dallas County?
FEMA flood maps for Dallas County
How does a project here connect to the grid?
Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.
Interconnection by market and utilityERCOT resource integration
What state and federal reviews can apply?
Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.
Statewide and federal contactsTexas decommissioning law
Check a specific property in Dallas County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 4
Collin · Cooke · Denton · Ellis · Erath · Fannin · Grayson · Hood · Hunt · Johnson · Kaufman · Navarro · Palo Pinto · Parker · Rockwall · Somervell · Tarrant · Wise