Home › Texas permits › Ellis County
Ellis County, Texas: solar, wind, and storage permits
Who to call and what to check for a solar, wind, or battery storage project in Ellis County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.
Who handles property records and taxes in Ellis County?
The Ellis County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.
Ellis County directory (Texas Comptroller)Lease rates and rollback taxes
Which TCEQ office covers Ellis County?
TCEQ Region 4, Dallas/Fort Worth
2309 Gravel Dr, Fort Worth TX 76118-6951
Main line: 817-588-5800 · Spills, 24 hours: 800-832-8224
Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.
TCEQ region directoryConstruction stormwater permit
Does Ellis County have zoning or a solar permit?
Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.
What energy projects are proposed in Ellis County?
ERCOT's August 2026 interconnection report lists 26 proposed energy projects in Ellis County (8 solar, 12 battery storage, 5 gas and 1 other), about 5,867 MW in all. 4 of the 26 have a signed interconnection agreement.
Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.
Scroll the table sideways to see every column.
| Project and connection point | Developer | Type | MW | Projected in service | Stage |
|---|---|---|---|---|---|
| Sol Marina SLF Energy CenterTap 345kV Stainback Switch (bus# 2217) – Big Onion Switch (bus# 2466) | Sol Marina Energy Center, LLC | Solar | 171.1 | Oct 2027 | Signed; security posted |
| Cumulus Grid BESS1906 Venus Switch Substation 345kV | Cumulus Grid, LLC | Battery storage (stand-alone) | 210.7 | Jan 2028 | Signed; security posted |
| Oystercatcher Solartap 345kV 1906 Venus - 68091 Navarro | Oystercatcher Solar, LLC | Solar | 198.4 | Jan 2027 | Signed Aug 2021 |
| Venus Mill Storage138 kV Tap #442 Rail Port - #1905 Griffith | AIH Texas Acquisitions, LLC | Battery storage (stand-alone) | 100.8 | Dec 2027 | Signed Dec 2025 |
| Dolomite Storage218 Rockett 69kV | BT Wilson Storage, LLC | Battery storage (stand-alone) | 125.7 | Dec 2026 | In study |
| Midlothian 4 repower1940 Midlothian ANP 345kV | MIDLOTHIAN ENERGY, LLC | Gas turbine | 18.0 | Jun 2027 | In study |
| Midlothian Unit 2 repower1939 Midlothian ELP 345kV | MIDLOTHIAN ENERGY, LLC | Gas turbine | 18.0 | Jun 2027 | In study |
| Midlothian Unit 3 repower1940 Midlothian ELP 345kV | MIDLOTHIAN ENERGY, LLC | Gas turbine | 18.0 | Jun 2027 | In study |
| Digital Ranch Gas#1906 Venus Switch 345 kV | MCV 1 LLC | Gas engines | 378.0 | Dec 2027 | In study |
| Tokyo TxHSR TPSS EW-1tap 138kV 2241 Ennis W - 2321 Waxahachie | Texas Central Rail Holdings, LLC | Other | 50.0 | Jul 2028 | In study |
| Bluebonnet Trail SolarTap 345 kV (#2427) WATMLL_W5 - (#2466) BIGONION_5 | Bluebonnet trail solar LLC | Solar | 150.9 | Sep 2028 | In study |
| Galaxy I SolarStainback Switch (bus #2217) - Elrod Switch (bus #3159) | Galaxy Solar, LLC | Solar | 99.4 | Oct 2028 | In study |
| Galaxy SolarStainback Switch (bus #2217) - Elrod Switch (bus #3159) | Galaxy Solar, LLC | Solar | 177.3 | Oct 2028 | In study |
| Galaxy StorageStainback Switch (bus #2217) - Elrod Switch (bus #3159) | Galaxy Solar, LLC | Battery storage (paired with solar) | 155.0 | Oct 2028 | In study |
| Two Step SolarTap 345kV 1907 Venus - 68091 Navarro | Two Step Solar, LLC | Solar | 401.6 | Sep 2029 | In study |
| Kickstart Energy Storage ITap 345 kV 1907 Venus Switch - 3383 BYNUM_5 | Kickstart Infrastructure LLC | Battery storage (stand-alone) | 1.4 | Sep 2029 | In study |
| Kickstart Energy Storage IITap 345 kV 1907 Venus Switch - 3383 BYNUM_5 | Kickstart Infrastructure LLC | Battery storage (stand-alone) | 1.4 | Sep 2029 | In study |
| Kickstart Energy Storage IIITap 345 kV #1906 VENUS_S5 to #68091 NAVARRO | Kickstart Infrastructure LLC | Battery storage (stand-alone) | 1.4 | Sep 2029 | In study |
| Kickstart Energy Storage IVTap 345 kV #1906 VENUS_S5 to #68091 NAVARRO | Kickstart Infrastructure LLC | Battery storage (stand-alone) | 1.4 | Sep 2029 | In study |
| Galaxy Solar 23/4-Breaker Ring Bus at 345kV Venus Switch (#1907) BKR 4920 - Navar... | Galaxy Solar 2, LLC | Solar | 301.6 | Oct 2029 | In study |
| Galaxy Storage 23/4-Breaker Ring Bus at 345kV Venus Switch (#1907) BKR 4920 - Navar... | Galaxy Solar 2, LLC | Battery storage (paired with solar) | 201.9 | Oct 2029 | In study |
| Kickstart Energy Storage V345 KV Venus 1906 to Fort Smith 3389 | Kickstart Infrastructure LLC | Battery storage (stand-alone) | 999.0 | Dec 2029 | In study |
| Kickstart Energy Storage VI345 KV Venus 1907 to Navarro 68091 | Kickstart Infrastructure LLC | Battery storage (stand-alone) | 1,026.2 | Dec 2029 | In study |
| Crape Myrtle SolarTap 345 kV 2255 OLDCNTRY_5 - 3376 NOTUS_5 | Crape Myrtle Solar LLC | Solar | 140.7 | Apr 2030 | In study |
| Victory Ellis – GasTap 345kV Nimbus (2249) – Big Onion (2466) & Stainback (2217) – Elr... | Victory Ellis, LLC | Gas turbine | 465.9 | Sep 2030 | In study |
| Victory Ellis–BESSTap 345kV Nimbus (2249) – Big Onion (2466) & Stainback (2217) – Elr... | Victory Ellis, LLC | Battery storage (paired with gas) | 453.0 | Sep 2030 | In study |
Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.
Where are the flood maps for Ellis County?
FEMA flood maps for Ellis County
How does a project here connect to the grid?
Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.
Interconnection by market and utilityERCOT resource integration
What state and federal reviews can apply?
Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.
Statewide and federal contactsTexas decommissioning law
Check a specific property in Ellis County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 4
Collin · Cooke · Dallas · Denton · Erath · Fannin · Grayson · Hood · Hunt · Johnson · Kaufman · Navarro · Palo Pinto · Parker · Rockwall · Somervell · Tarrant · Wise