Home › Texas permits › Van Zandt County
Van Zandt County, Texas: solar, wind, and storage permits
Who to call and what to check for a solar, wind, or battery storage project in Van Zandt County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.
Who handles property records and taxes in Van Zandt County?
The Van Zandt County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.
Van Zandt County directory (Texas Comptroller)Lease rates and rollback taxes
Which TCEQ office covers Van Zandt County?
TCEQ Region 5, Tyler
2916 Teague Dr, Tyler TX 75701-3734
Main line: 903-535-5100 · Spills, 24 hours: 800-832-8224
Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.
TCEQ region directoryConstruction stormwater permit
Does Van Zandt County have zoning or a solar permit?
Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.
What energy projects are proposed in Van Zandt County?
ERCOT's August 2026 interconnection report lists 8 proposed energy projects in Van Zandt County (2 solar and 6 battery storage), about 986 MW in all. 4 of the 8 have a signed interconnection agreement.
Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.
Scroll the table sideways to see every column.
| Project and connection point | Developer | Type | MW | Projected in service | Stage |
|---|---|---|---|---|---|
| Amador Storage6833 Explorer Switching Station 138kV | BT Amador Storage, LLC | Battery storage (stand-alone) | 102.4 | Jan 2027 | Signed; security posted |
| Caney Creek SolarTap 138kV 6829 Glen Pine - 6833 Explorer | HEP Aquamarine Holdings LLC | Solar | 121.0 | Jun 2027 | Signed; security posted |
| Whiskey BESS6828 Canton Tap 138 kV | Whiskey BESS LLC | Battery storage (stand-alone) | 153.7 | Jul 2027 | Signed Mar 2025 |
| Zorro BESS138 kV Ben Wheeler (Bus# 6852) | ZORRO BESS LLC | Battery storage (stand-alone) | 153.7 | Aug 2027 | Signed Mar 2025 |
| Edgewood BESS 1Tap Edgewood 138kV bus(3181) to CANTNSW_8 (3174) | Tempus Power management LLC | Battery storage (stand-alone) | 102.1 | Mar 2028 | In study |
| Edgewood BESS 2Tap Edgewood 138kV bus(3181) to 3174 | Tempus Power management LLC | Battery storage (stand-alone) | 102.1 | Mar 2028 | In study |
| Goldfinch SolarTap Connection Bus 2485 Poetry Switch to 3103 Shamburger Switch | BT DJ4M Solar, LLC | Solar | 150.8 | Mar 2029 | In study |
| Goldfinch StorageTap Connection Bus 2485 Poetry Switch – 3223 Shamburger Switch | BT DJ4M Solar, LLC | Battery storage (paired with solar) | 100.4 | Mar 2030 | In study |
Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.
Where are the flood maps for Van Zandt County?
FEMA flood maps for Van Zandt County
How does a project here connect to the grid?
Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.
Interconnection by market and utilityERCOT resource integration
What state and federal reviews can apply?
Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.
Statewide and federal contactsTexas decommissioning law
Check a specific property in Van Zandt County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 5
Anderson · Bowie · Camp · Cass · Cherokee · Delta · Franklin · Gregg · Harrison · Henderson · Hopkins · Lamar · Marion · Morris · Panola · Rains · Red River · Rusk · Smith · Titus · Upshur · Wood