Lamar County, Texas: solar, wind, and storage permits
Who to call and what to check for a solar, wind, or battery storage project in Lamar County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.
Who handles property records and taxes in Lamar County?
The Lamar County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.
Lamar County directory (Texas Comptroller)Lease rates and rollback taxes
Which TCEQ office covers Lamar County?
TCEQ Region 5, Tyler
2916 Teague Dr, Tyler TX 75701-3734
Main line: 903-535-5100 · Spills, 24 hours: 800-832-8224
Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.
TCEQ region directoryConstruction stormwater permit
Does Lamar County have zoning or a solar permit?
Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.
What energy projects are proposed in Lamar County?
ERCOT's August 2026 interconnection report lists 24 proposed energy projects in Lamar County (13 solar, 1 wind, 7 battery storage and 3 gas), about 6,054 MW in all. 13 of the 24 have a signed interconnection agreement, and 8 have been energized or approved to connect.
Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.
Scroll the table sideways to see every column.
| Project and connection point | Developer | Type | MW | Projected in service | Stage |
|---|---|---|---|---|---|
| MRG GOODY SOLARTap 138 kV Toco Switch (#1700) – Paris Switch (#1693) | MRG GOODY SOLAR PROJECT, LLC | Solar | 170.8 | Aug 2026 | Approved to connect |
| MRG Goody StorageTap 138 kV Toco Switch (#1700) – Paris Switch (#1693) | MRG Goody Solar Project LLC | Battery storage | 52.3 | Aug 2026 | Approved to connect |
| Baker Branch Solartap 345kV 1692 Paris - 1690 Valley | Mockingbird Solar Center, LLC | Solar | 469.4 | Sep 2026 | Approved to connect |
| Delilah Solar 1tap both 345kV 1685 FarmersVl - 1695 Moses ckts | Delilah Solar Energy LLC | Solar | 300.0 | Dec 2026 | Approved to connect |
| Delilah Solar 2345 kV TTRSW 11688 | Delilah Solar Energy II LLC | Solar | 317.6 | Dec 2026 | Approved to connect |
| Samson Solar 1tap both 345kV 1685 FarmersVl - 1695 Moses ckts | Samson Solar Energy LLC | Solar | 250.0 | Dec 2026 | Approved to connect |
| Samson Solar 2345 kV TTRSW 11688 | Samson Solar Energy II LLC | Solar | 203.0 | Dec 2026 | Approved to connect |
| Samson Solar 3tap both 345kV 1685 FarmersVl - 1695 Moses ckts | Samson Solar Energy III LLC | Solar | 250.0 | Dec 2026 | Approved to connect |
| Rowdy Creek SolarWoodfin Switch (#1465) 345kV | Rowdy Creek Solar LLC | Solar | 351.8 | Dec 2027 | Signed; security posted |
| Echols Grove SolarTap 138kV Hawk Hollow Switch (#11768) and Lamar Blossom Switch (#11... | Echols Grove, LLC | Solar | 201.6 | Jan 2028 | Signed; security posted |
| Star Dairy SolarTap 345kV 1692 PARIS_SW1_5 -- 11699 WOODARD_5 | Star Dairy Solar LLC | Solar | 115.6 | Jul 2027 | Signed Dec 2024 |
| Star Dairy StorageTap 345kV 1692 PARIS_SW1_5 -- 11699 WOODARD_5 | Star Dairy Storage | Battery storage (paired with solar) | 205.2 | Jul 2027 | Signed Dec 2024 |
| Bug Tussle Wind ProjectTap 1729 Valley South and 1692 Paris | Bug Tussle Wind, LLC | Wind | 396.8 | Sep 2028 | Signed Jul 2024 |
| Lamar Unit 1 Repower1692 Paris Switch Station 345kV | La Frontera Holdings, LLC | Gas combined cycle | 66.0 | Dec 2027 | In study |
| Arc Energy StorageTap 138kV 1693 Paris Switch - 11806 ENLOE T8 | Paris Energy Storage, LLC | Battery storage (stand-alone) | 204.5 | Jun 2028 | In study |
| Roxton SolarTap 138 KV Bois Pump (1835) - Brookston (1833) | Roxton Solar, LLC | Solar | 116.8 | Jul 2028 | In study |
| Roxton StorageTap 138 KV Bois Pump (1835) - Brookston (1833) | Roxton Solar, LLC | Battery storage (paired with solar) | 102.0 | Jul 2028 | In study |
| Lan Battery SLFTap 345kV 1729 Valley South – 1692 Paris Switch | BR Solar, LLC | Battery storage (paired with solar) | Self-limiting | Aug 2028 | In study |
| Lan Solar SLFTap 345kV 1729 Valley South – 1692 Paris Switch | BR Solar, LLC | Solar | 182.2 | Aug 2028 | In study |
| Mud Cat Solar SLFTap 138KV 11768 Hawk Hollow – 1768 Deport | Mud Cat Solar, LLC | Solar | 100.5 | Sep 2028 | In study |
| Mud Cat Storage SLF11768 Hawk Hollow – 1768 Deport 138kV | Mud Cat Solar, LLC | Battery storage (paired with solar) | Self-limiting | Sep 2028 | In study |
| Baker Branch BESSPacific Switch (PACSW) 345 kV Bus 11683 | Mockingbird Storage Center, LLC | Battery storage (paired with solar) | 287.2 | Dec 2029 | In study |
| Southeast Oklahoma Pumped Storage1692 Paris Switch 345kV | Apex Energy Solutions, LLC | WAT | 1,232.0 | Jan 2030 | In study |
| North Royal Thermal (TEF- Due Diligence)Tap 345kV 1695 MOSES_5 - 11699 WOODARD_5 | Invenergy Energy Transition Development LLC | Gas turbine | 479.0 | Aug 2030 | In study |
Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.
Where are the flood maps for Lamar County?
FEMA flood maps for Lamar County
How does a project here connect to the grid?
Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.
Interconnection by market and utilityERCOT resource integration
What state and federal reviews can apply?
Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.
Statewide and federal contactsTexas decommissioning law
Check a specific property in Lamar County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 5
Anderson · Bowie · Camp · Cass · Cherokee · Delta · Franklin · Gregg · Harrison · Henderson · Hopkins · Marion · Morris · Panola · Rains · Red River · Rusk · Smith · Titus · Upshur · Van Zandt · Wood