Zapata County, Texas: solar, wind, and storage permits
Who to call and what to check for a solar, wind, or battery storage project in Zapata County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.
Who handles property records and taxes in Zapata County?
The Zapata County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.
Zapata County directory (Texas Comptroller)Lease rates and rollback taxes
Which TCEQ office covers Zapata County?
TCEQ Region 16, Laredo
707 E Calton Rd, Ste 304, Laredo TX 78041-3887
Main line: 956-791-6611 · Spills, 24 hours: 800-832-8224
Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.
TCEQ region directoryConstruction stormwater permit
Does Zapata County have zoning or a solar permit?
Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.
What energy projects are proposed in Zapata County?
ERCOT's August 2026 interconnection report lists 27 proposed energy projects in Zapata County (10 solar, 9 wind and 8 battery storage), about 6,291 MW in all. 5 of the 27 have a signed interconnection agreement.
Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.
Scroll the table sideways to see every column.
| Project and connection point | Developer | Type | MW | Projected in service | Stage |
|---|---|---|---|---|---|
| Cascabel Wind 1345 kV Rapido Substation (New ETT Substation) tapping the existing... | Vaquero Wind Energy, LLC | Wind | 197.8 | Dec 2027 | Signed; security posted |
| Cascabel Wind 2345 kV Rapido Substation (New ETT Substation) tapping the existing... | Vaquero Wind Energy, LLC | Wind | 197.8 | Dec 2027 | Signed; security posted |
| Corralitos Wind 1Tap 345kV 80225 CENIZO7C - 80307 DELSOL7C (New ETT Tiempo Substation) | Vaquero Wind Energy, LLC | Wind | 196.1 | Dec 2027 | Signed; security posted |
| Corralitos Wind 2Tap 345kV 80225 CENIZO7C - 80307 DELSOL7C (New ETT Tiempo Substation) | Vaquero Wind Energy, LLC | Wind | 195.4 | Dec 2027 | Signed; security posted |
| Falcon Zapata Storage 138Tap 138kV 8299 Zapata - 8957 Lopeno | Falcon BESS, LLC | Battery storage (stand-alone) | 200.8 | Mar 2028 | Signed; security posted |
| Vaquero 1 Windtap 345kV 8905 N Edinb - 8455 Lon Hill | Enerverse | Wind | 400.0 | Jan 2027 | In study |
| Slate Solar ProjectTap 138kV 8646 Rio Bravo - 8985 San Ygancio | Ignis TX Solar Three LLC | Solar | 104.9 | Oct 2027 | In study |
| Sierra Madre Solartap 345kV 80307 Del Sol - 80225 Cenizo | Sierra Madre Solar LLC | Solar | 255.2 | Dec 2027 | In study |
| Zelus BESSthe 138 kV Zapata Substation (#8299; AEP) | BRP Zelus BESS LLC | Battery storage (stand-alone) | 201.0 | Dec 2027 | In study |
| Rancho Grande Solar345 kV Tiempo Substation #80224 | Bordas Renewable Energy, LLC | Solar | 251.6 | May 2028 | In study |
| Barrosos Creek Wind 3#80227 Rapido 345 kV | Cascabel Wind Energy, LLC | Wind | 197.8 | May 2028 | In study |
| Barrosos Creek Wind 4#80227 Rapido 345 kV | Cascabel Wind Energy, LLC | Wind | 197.8 | May 2028 | In study |
| Corralitos Wind 3ETT 345 kV Tiempo #80224 Substation (Tap on 345kV 80225 CENIZO7C -... | Las Crestas Wind Energy, LLC | Wind | 196.1 | May 2028 | In study |
| Corralitos Wind 4ETT 345 kV Tiempo #80224 Substation (Tap on 345kV 80225 CENIZO7C -... | Las Crestas Wind Energy, LLC | Wind | 195.4 | May 2028 | In study |
| Freedom Falcon BESSTap 345kV #80224 Tiempo - #80227 Rapido | Falcon BESS, LLC | Battery storage (stand-alone) | 501.9 | Aug 2028 | In study |
| Quarter Ranch Solar80223 Cenizo Substation 345kV | Gransolar Texas Three LLC | Solar | 154.1 | Oct 2028 | In study |
| Big River BESStap 138kV 8299 Zapata - 8957 Lopeno4A | Rio Grande River Solar LLC | Battery storage (paired with solar) | 51.3 | Dec 2028 | In study |
| Big River Solartap 138kV 8299 Zapata - 8957 Lopeno4A | Rio Grande River Solar LLC | Solar | 104.3 | Dec 2028 | In study |
| La Morena Energy Center BESSTap 345 kV 80225 CENIZO7C - 80307 DELSOL7C | Adapture Solar Development | Battery storage (paired with solar) | 250.0 | May 2029 | In study |
| La Morena Energy Center SolarTap 345 kV (80225) CENIZO7C - (80307) DELSOL7C | Adapture Solar Development | Solar | 250.0 | May 2029 | In study |
| Tetris SolarTAP 345kV 80307 Del Sol 7C - 80225 Cenizo 7C | NextEra Energy Interconnection Holdings LLC | Solar | 359.0 | Jul 2029 | In study |
| Falcon BESSTap 345kV #80225 CENIZO to #80307 DEL SOL | Falcon Energy Project, LLC | Battery storage (paired with solar) | 516.7 | Dec 2029 | In study |
| Falcon SolarTap 345kV #80225 Cenizo7C to #80307 Del Sol7C | Falcon Energy Project, LLC | Solar | 502.0 | Dec 2029 | In study |
| Wallflower Energy StorageTap the 345 kV Cenizo (#80225) - Del Sol (#80307) line | Wallflower Energy Storage | Battery storage (paired with solar) | 209.2 | Dec 2029 | In study |
| Wallflower SolarTap the 345 kV Cenizo (#80225) - Del Sol (#80307) line. | Wallflower Solar, LLC | Solar | 201.2 | Dec 2029 | In study |
| Falcon II BESS8004 Revilla 138 kV | Falcon Energy Project | Battery storage (paired with solar) | 103.3 | Feb 2032 | In study |
| Falcon II Solar8004 Revilla 138 kV | Falcon Energy Project | Solar | 100.3 | Feb 2032 | In study |
Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.
Where are the flood maps for Zapata County?
FEMA flood maps for Zapata County
How does a project here connect to the grid?
Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.
Interconnection by market and utilityERCOT resource integration
What state and federal reviews can apply?
Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.
Statewide and federal contactsTexas decommissioning law
Check a specific property in Zapata County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 16
Dimmit · Duval · Kinney · La Salle · Maverick · McMullen · Val Verde · Webb · Zavala