Home › Texas permits › Dimmit County
Dimmit County, Texas: solar, wind, and storage permits
Who to call and what to check for a solar, wind, or battery storage project in Dimmit County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.
Who handles property records and taxes in Dimmit County?
The Dimmit County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.
Dimmit County directory (Texas Comptroller)Lease rates and rollback taxes
Which TCEQ office covers Dimmit County?
TCEQ Region 16, Laredo
707 E Calton Rd, Ste 304, Laredo TX 78041-3887
Main line: 956-791-6611 · Spills, 24 hours: 800-832-8224
Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.
TCEQ region directoryConstruction stormwater permit
Does Dimmit County have zoning or a solar permit?
Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.
What energy projects are proposed in Dimmit County?
ERCOT's August 2026 interconnection report lists 12 proposed energy projects in Dimmit County (3 solar and 9 battery storage), about 1,294 MW in all. 2 of the 12 have a signed interconnection agreement.
Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.
Scroll the table sideways to see every column.
| Project and connection point | Developer | Type | MW | Projected in service | Stage |
|---|---|---|---|---|---|
| Rose Quartz BESSTap 138kV 8283 Asherton - 8613 Bigwells | Rose Quartz BESS, LLC | Battery storage (stand-alone) | 101.4 | Dec 2026 | Signed Jul 2026 |
| Desert Palm BESS78280 Bevo Substation 138 kV | Desert Palm BESS, LLC | Battery storage (stand-alone) | 201.3 | Sep 2028 | Signed Jul 2026 |
| Saluga Ranch StorageAsherton 8283 - Big wells 8613 -138 kV | Saluga Ranch Energy, LLC | Battery storage (stand-alone) | 125.4 | Aug 2027 | In study |
| Steppe Reserve Storage8283 Asherton 138 kV | KCE TX 25, LLC | Battery storage (stand-alone) | 51.9 | Jan 2028 | In study |
| Sugarloaf BESS(#80481) PILONCIL4 138KV | Sugarloaf Clean Energy LLC | Battery storage (stand-alone) | 100.6 | Jan 2028 | In study |
| Wintergarden BESS8970 Catarina 138 kV | Wintergarden BESS LLC | Battery storage (stand-alone) | 201.2 | Jun 2028 | In study |
| Wild Horse Desert SolarTap 138kV 8613 Big Well - 8212 Dilley Switch | Wild Horse Desert Solar, LLC | Solar | 120.0 | Jul 2028 | In study |
| Wild Horse Desert StorageTap 138kV 8613 Big Well - 8212 Dilley Switch | Wild Horse Desert Solar, LLC | Battery storage (paired with solar) | 90.3 | Jul 2028 | In study |
| Velado Solar SLFTap 138kV 78281 Dimmit - 8274 Conoco Chittam | Velado Solar, LLC | Solar | 115.2 | Sep 2028 | In study |
| Velado Storage SLFTap 138kv 78281 Dimmit - 8274 Conoco Chittam. | Velado Solar, LLC | Battery storage (paired with solar) | 115.2 | Sep 2028 | In study |
| 7L Solar SLFTap 69kV 5870 Brundage - 5868 Big Wells | 7L Solar, LLC | Solar | 71.6 | Nov 2029 | In study |
| 7L Storage SLFTap 69kV 5870 Brundage - 5868 Big Wells | 7L Solar, LLC | Battery storage (paired with solar) | Self-limiting | Nov 2029 | In study |
Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.
Where are the flood maps for Dimmit County?
FEMA flood maps for Dimmit County
How does a project here connect to the grid?
Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.
Interconnection by market and utilityERCOT resource integration
What state and federal reviews can apply?
Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.
Statewide and federal contactsTexas decommissioning law
Check a specific property in Dimmit County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.