Nueces County, Texas: solar, wind, and storage permits

Contacts checked 2026-09-26 · From official state and federal directories

Who to call and what to check for a solar, wind, or battery storage project in Nueces County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.

Who handles property records and taxes in Nueces County?

The Nueces County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.

Nueces County directory (Texas Comptroller)Lease rates and rollback taxes

Which TCEQ office covers Nueces County?

TCEQ Region 14, Corpus Christi
500 North Shoreline Blvd, Ste 500, Corpus Christi TX 78401-0318
Main line: 361-881-6900 · Spills, 24 hours: 800-832-8224

Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.

TCEQ region directoryConstruction stormwater permit

Does Nueces County have zoning or a solar permit?

Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.

What energy projects are proposed in Nueces County?

ERCOT's August 2026 interconnection report lists 12 proposed energy projects in Nueces County (2 solar, 8 battery storage and 2 gas), about 2,227 MW in all. 7 of the 12 have a signed interconnection agreement, and 1 has been energized or approved to connect.

Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.

Scroll the table sideways to see every column.

Project and connection pointDeveloperTypeMWProjected in serviceStage
Lynx Energy Storage138KV Tap 8921 Terra Verde - 8518 KingsvilleCorpus Battery Storage, LLCBattery storage (stand-alone)125.3May 2026Approved to connect
Noria Solar DCC85000 Nelson Sharpe 345kVNoria Hondo Solar LLCSolar145.0Apr 2028Signed; security posted
Noria Storage85000 Nelson Sharpe 345kVNoria Hondo Solar LLCBattery storage (paired with solar)75.0Apr 2028Signed; security posted
Blanquilla BESSTap 138kV 8452 LON_HILL4A - 8441 NUECES_B4ABlanquilla BESS LLCBattery storage (stand-alone)200.8May 2028Signed; security posted
Sunscape Renewable Energy Solar SLFBus# 8455 Lon C Hill to Bus# 80078 Reforzar 345 kV LineSunscape Renewable Energy LLCSolar522.8Oct 2028Signed; security posted
Sunscape Renewable Energy Storage SLFTap 345kV 8455 Lon C Hill -- 80078 ReforzarSunscape Renewable Energy LLCBattery storage (paired with solar)Self-limitingOct 2028Signed; security posted
NavBoot BESS8858 MCKENZIE4A 138kVNavboot BESS LLCBattery storage (stand-alone)303.7Nov 2027Signed Oct 2025
GOTHAM BESS5640 DRISCOLLSUB9 69kVAEU BATTERY PROJECT IV LLCBattery storage (stand-alone)151.2Mar 2027In study
Barbara BESSLINE TAP OF WESTSIDE (8485) AND WEIL TRACT (8482) 138 KV TRANSMISSI...Barbara BESS LLCBattery storage (stand-alone)200.5May 2028In study
Jalisco Cogen8475 JAVELINA4A 138 KVHEP Power Generation, LLCGas combined cycle167.8May 2029In study
Jalisco Peaker8475 JAVELINA4A 138kVHEP Power Generation, LLCGas turbine183.6May 2029In study
Violet StorageMcKenzie Road (8858) 138 kV SubstationVIOLET STORAGEBattery storage (stand-alone)151.0Jul 2029In study

Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.

Where are the flood maps for Nueces County?

FEMA flood maps for Nueces County

How does a project here connect to the grid?

Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.

Interconnection by market and utilityERCOT resource integration

What state and federal reviews can apply?

Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.

Statewide and federal contactsTexas decommissioning law

Check a specific property in Nueces County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Open Quicksand Check

Other counties served by TCEQ Region 14

Aransas · Bee · Calhoun · DeWitt · Goliad · Gonzales · Jackson · Jim Wells · Kleberg · Lavaca · Live Oak · Refugio · San Patricio · Victoria

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not legal advice. Found an error? Let us know.