Home › Texas permits › Hidalgo County
Hidalgo County, Texas: solar, wind, and storage permits
Who to call and what to check for a solar, wind, or battery storage project in Hidalgo County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.
Who handles property records and taxes in Hidalgo County?
The Hidalgo County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.
Hidalgo County directory (Texas Comptroller)Lease rates and rollback taxes
Which TCEQ office covers Hidalgo County?
TCEQ Region 15, Harlingen
1804 W Jefferson Ave, Harlingen TX 78550-5247
Main line: 956-425-6010 · Spills, 24 hours: 800-832-8224
Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.
TCEQ region directoryConstruction stormwater permit
Does Hidalgo County have zoning or a solar permit?
Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.
What energy projects are proposed in Hidalgo County?
ERCOT's August 2026 interconnection report lists 26 proposed energy projects in Hidalgo County (4 solar, 1 wind, 20 battery storage and 1 gas), about 4,749 MW in all. 7 of the 26 have a signed interconnection agreement, and 2 have been energized or approved to connect.
Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.
Scroll the table sideways to see every column.
| Project and connection point | Developer | Type | MW | Projected in service | Stage |
|---|---|---|---|---|---|
| North Edinburg BESS 1TSP Station Name: North Edinburg | Edinburg ESS Assets LLC | Battery storage (stand-alone) | 10.0 | Aug 2026 | Approved to connect |
| Gunnar BESS8029 CLOSNER4A 138kV | Gunnar Reliability Project LLC | Battery storage (stand-alone) | 154.8 | Dec 2026 | Energized |
| Big Five StorageTap 138kV (5784) Redgtss - (8380) Nedina | TX BESS 3 LLC | Battery storage (stand-alone) | 102.2 | Jan 2028 | Under construction |
| Grapefruit SolarNorth Edinburg (Bus #8905) - Reforzar (Bus # 80078) 345kV | Grapefruit Solar LLC | Solar | 291.4 | Dec 2028 | Signed; security posted |
| Monte Cristo II Wind8574 Pomelo 345kV | Monte Cristo Windpower II, LLC | Wind | 233.9 | Dec 2028 | Signed; security posted |
| Val Vista Grid BESS 1Tap 345kV 8383 North Edinburg - 80137 Stewart Road | Val Vista Grid, LLC | Battery storage (stand-alone) | 209.3 | Mar 2029 | Signed Dec 2025 |
| Val Vista Grid BESS 2Tap 345kV 8383 North Edinburg - 80137 Stewart Road | Val Vista Grid, LLC | Battery storage (stand-alone) | 210.6 | Mar 2029 | Signed Dec 2025 |
| Palmvalley StorageFrontera (#8980) | Palm Valley BESS LLC | Battery storage (stand-alone) | 100.0 | May 2027 | In study |
| Anawa La BESSTap 138KV 8394 Liston- 8392 Bates | Anawa La Solar LLC | Battery storage (paired with solar) | 103.7 | Aug 2027 | In study |
| Anawa La SolarTAP 138 KV 8394 LISTON - 8392 BATES | Anawa La Solar LLC | Solar | 93.3 | Aug 2027 | In study |
| Bronze Quinta StorageS_MCALLN 8371 (S. McAllen 138kV Substation) | KCE TX 28, LLC | Battery storage (stand-alone) | 103.5 | Jan 2028 | In study |
| Hawkins BESS85005 ELGATO4A 138 kV | BRP BLUE TOPAZ 7, LLC | Battery storage (stand-alone) | 150.4 | Jan 2028 | In study |
| Camellia StorageTap 138 kV 8358 | Camellia Storage Project LLC | Battery storage (stand-alone) | 90.8 | Jun 2028 | In study |
| PSE Chihuahua TX StorageTap 138kV 8392 Bates – 8394 Liston | PureSky Development Inc | Battery storage (stand-alone) | 200.0 | Jun 2028 | In study |
| PSE Minnesota TX StorageTap 138kV 8372 North Pharr – 8906 North Alamo | PureSky Development Inc | Battery storage (stand-alone) | 94.0 | Jun 2028 | In study |
| PSE Richardson TX StorageTAP 138KV 8374 SOUTH EAST EDINBURG - 8029 CLOSNER | PureSky Development Inc. | Battery storage (stand-alone) | 100.0 | Jun 2028 | In study |
| Palladium StorageTap 138 kV 8656 Luna - 8033 Pantera | Palladium Energy Storage LLC | Battery storage (stand-alone) | 156.3 | Jun 2028 | In study |
| Eligius BESStap 138kV Liston (#8394) – JL Bates (#8392) line, AEP | Eligius Storage LLC | Battery storage (stand-alone) | 174.7 | Nov 2028 | In study |
| Borderland ESCtap 138kV 8380 NEDIN4A – 8632 NMCALLEN4C | FRESH AIR ENERGY II, LLC | Battery storage (stand-alone) | 200.0 | Nov 2028 | In study |
| McMEXICO STORAGE8644 Trade Zone 138kV | FRESH AIR ENERGY II, LLC | Battery storage (stand-alone) | 201.9 | Nov 2028 | In study |
| Anawa La GasListon 138 KV to Bates 138 KV | Anawa La Solar LLC | Gas combined cycle | 1,220.0 | Dec 2028 | In study |
| Donna BESSTap 345 kV 80137 Stewart Road - 8383 North Edinburg | Donna Solar LLC | Battery storage (paired with solar) | 53.9 | Feb 2029 | In study |
| Donna SolarTap 345 kV (80137) Stewart Road - (8383) North Edinburg CKT ID#01 | Donna Solar LLC | Solar | 168.1 | Feb 2029 | In study |
| Sullivan BESSTap 138kV 8798 La Grulla - 8355 Goodwin | Sullivan Solar LLC | Battery storage (paired with solar) | 72.2 | Feb 2029 | In study |
| Sullivan SolarTap 138kV 8798 La Grulla - 8355 Goodwin | Sullivan Solar LLC | Solar | 170.7 | Feb 2029 | In study |
| Billie StorageTap 138kV 8357 North Weslaco – 8358 North Mercedes | Weslaco Storage LLC | Battery storage (stand-alone) | 83.8 | Sep 2029 | In study |
Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.
Where are the flood maps for Hidalgo County?
FEMA flood maps for Hidalgo County
How does a project here connect to the grid?
Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.
Interconnection by market and utilityERCOT resource integration
What state and federal reviews can apply?
Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.
Statewide and federal contactsTexas decommissioning law
Check a specific property in Hidalgo County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 15
Brooks · Cameron · Jim Hogg · Kenedy · Starr · Willacy