Quicksand Check

Home › Texas permits › Swisher County

Swisher County, Texas: solar, wind, and storage permits

Contacts checked 2026-09-26 · From official state and federal directories

Who to call and what to check for a solar, wind, or battery storage project in Swisher County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.

Who handles property records and taxes in Swisher County?

The Swisher County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.

Swisher County directory (Texas Comptroller)Lease rates and rollback taxes

Which TCEQ office covers Swisher County?

TCEQ Region 1, Amarillo
5809 S. Western St., Ste 260, Amarillo TX 79110-3631
Main line: 806-353-9251 · Spills, 24 hours: 800-832-8224

Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.

TCEQ region directoryConstruction stormwater permit

Does Swisher County have zoning or a solar permit?

Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.

What energy projects are proposed in Swisher County?

ERCOT's August 2026 interconnection report lists 7 proposed energy projects in Swisher County (3 solar, 1 wind and 3 battery storage), about 2,049 MW in all. 2 of the 7 have a signed interconnection agreement.

Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.

Scroll the table sideways to see every column.

Project and connection pointDeveloperTypeMWProjected in serviceStage
Hornet Solar II SLFOzark Trail Switch 345kV substation (Bus #23901)Hornet Solar II LLCSolar201.5Jul 2028Signed; security posted
Hornet Storage II SLFOzark Trail Switch 345kV substation (Bus # 23901)Hornet Storage II LLCBattery storage (paired with solar)Self-limitingJul 2028Signed; security posted
Stem Solartap 345kV 23914 Tule Canyon - 23912 OgallalaInnovative Solar 134, LLCSolar200.0Aug 2025In study
Hornet Energy Storage SLF23901 OZARKTRAIL_5 345kVHornet Energy Storage LLCBattery storage (stand-alone)Self-limitingSep 2028In study
Frye Storagenew 345kV sub Kress connecting both 23912 Ogallala - 23914 Tule Can...Hecate Energy Frye Storage LLCBattery storage (paired with solar)503.9Dec 2028In study
Commodus 2 SolarTapping the 345 kV Double-Circuit Line from Tule Canyon (Bus# 23914...IP Blackwell II, LLCSolar502.1Jul 2029In study
Commodus 2 WindTapping the 345 kV Double-Circuit Line from Tule Canyon (Bus# 23914...IP Blackwell II, LLCWind641.5Jul 2029In study

Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.

Where are the flood maps for Swisher County?

FEMA flood maps for Swisher County

How does a project here connect to the grid?

Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.

Interconnection by market and utilityERCOT resource integration

What state and federal reviews can apply?

Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.

Statewide and federal contactsTexas decommissioning law

Check a specific property in Swisher County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Open Quicksand Check

Other counties served by TCEQ Region 1

Armstrong · Briscoe · Carson · Castro · Childress · Collingsworth · Dallam · Deaf Smith · Donley · Gray · Hall · Hansford · Hartley · Hemphill · Hutchinson · Lipscomb · Moore · Ochiltree · Oldham · Parmer · Potter · Randall · Roberts · Sherman · Wheeler

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not legal advice. Found an error? Let us know.