Castro County, Texas: solar, wind, and storage permits

Contacts checked 2026-09-26 · From official state and federal directories

Who to call and what to check for a solar, wind, or battery storage project in Castro County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.

Who handles property records and taxes in Castro County?

The Castro County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.

Castro County directory (Texas Comptroller)Lease rates and rollback taxes

Which TCEQ office covers Castro County?

TCEQ Region 1, Amarillo
5809 S. Western St., Ste 260, Amarillo TX 79110-3631
Main line: 806-353-9251 · Spills, 24 hours: 800-832-8224

Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.

TCEQ region directoryConstruction stormwater permit

Does Castro County have zoning or a solar permit?

Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.

What energy projects are proposed in Castro County?

ERCOT's August 2026 interconnection report lists 7 proposed energy projects in Castro County (4 solar, 1 wind and 2 battery storage), about 2,304 MW in all. 3 of the 7 have a signed interconnection agreement.

Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.

Scroll the table sideways to see every column.

Project and connection pointDeveloperTypeMWProjected in serviceStage
Nazareth Solartap 345kV 23914 Tule Canyon - 23912 Ogallala C2TX Nazareth Solar, LLCSolar203.0Aug 2027Signed; security posted
Castro Solar23912 Ogallala 345kVCastro Solar One, LLCSolar224.7Sep 2028Signed Nov 2020
Acker BESS23912 Ogallala 345 kVOgallala BESS LLCBattery storage (stand-alone)301.0Apr 2029Signed Apr 2025
Scarlet Solartap 345kV 23912 Ogallala - 23910 WindmillInnovative Solar 416, LLCSolar180.0Aug 2025In study
Ogalalla Storage23912 OGALLALA_5 345kVHecate Energy Ogalalla Solar LLCBattery storage (stand-alone)251.6Apr 2028In study
Cavell SolarTap 345kV 23910 Windmill - 23912 Ogallala Ckt 1IP Cavell, LLCSolar502.1Jul 2029In study
Cavell Windtap 345kV 23910 Windmill - 23912 Ogallala Ckt 1IP Cavell, LLCWind641.2Jul 2029In study

Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.

Where are the flood maps for Castro County?

FEMA flood maps for Castro County

How does a project here connect to the grid?

Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.

Interconnection by market and utilityERCOT resource integration

What state and federal reviews can apply?

Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.

Statewide and federal contactsTexas decommissioning law

Check a specific property in Castro County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Open Quicksand Check

Other counties served by TCEQ Region 1

Armstrong · Briscoe · Carson · Childress · Collingsworth · Dallam · Deaf Smith · Donley · Gray · Hall · Hansford · Hartley · Hemphill · Hutchinson · Lipscomb · Moore · Ochiltree · Oldham · Parmer · Potter · Randall · Roberts · Sherman · Swisher · Wheeler

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not legal advice. Found an error? Let us know.