Schleicher County, Texas: solar, wind, and storage permits

Contacts checked 2026-09-26 · From official state and federal directories

Who to call and what to check for a solar, wind, or battery storage project in Schleicher County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.

Who handles property records and taxes in Schleicher County?

The Schleicher County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.

Schleicher County directory (Texas Comptroller)Lease rates and rollback taxes

Which TCEQ office covers Schleicher County?

TCEQ Region 8, San Angelo
622 S Oakes, Ste K, San Angelo TX 76903-7035
Main line: 325-655-9479 · Spills, 24 hours: 800-832-8224

Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.

TCEQ region directoryConstruction stormwater permit

Does Schleicher County have zoning or a solar permit?

Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.

What energy projects are proposed in Schleicher County?

ERCOT's August 2026 interconnection report lists 11 proposed energy projects in Schleicher County (4 solar, 2 wind and 5 battery storage), about 2,250 MW in all. 3 of the 11 have a signed interconnection agreement.

Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.

Scroll the table sideways to see every column.

Project and connection pointDeveloperTypeMWProjected in serviceStage
Rockefeller Storage76003 Big Hill 345kVMittel Rockefeller Storage LLCBattery storage (stand-alone)206.8Jun 2027Signed; security posted
Cold Creek Solar 2Tap 345kV line Big Hill (#76003) - Twin Buttes (#76009)Cold Creek Solar and Storage LLCSolar431.9May 2028Signed Apr 2025
Cold Creek Storage 2Tap 345kV line Big Hill (#76003) - Twin Buttes (#76009)Cold Creek Solar and Storage LLCBattery storage (paired with solar)171.8May 2028Signed Apr 2025
Cashel BESS6500 Live Oak AEP 138kVTIPPSOL LLCBattery storage (stand-alone)150.4Mar 2028In study
Tipperary Solar6498 Live Oak AEP 69kVTippsolSolar60.2Mar 2028In study
Sombrero SolarTap 345kV 76003 Big Hill - 60708 OrstedAurora Solar LLCSolar351.9May 2028In study
Proving Ground BESSTap 138kV 6500 Live Oak - 6490 SantiagoLantana Solar LLCBattery storage (paired with solar)51.4Jun 2028In study
Proving Ground SolarTap 138 kV Live Oak (6500) - Santiago (6490)Lantana Solar LLCSolar82.1Jun 2028In study
Live Oak Wind II#76003 Big Hill 345kVENGIE IR Holdings LLCWind302.6Sep 2028In study
Easy Battery Energy Storage CenterTap 345 kV 76003 Big Hill to 76005 Schneeman DrawEasy Wind Energy Center, LLCBattery storage (paired with wind)200.0Jun 2029In study
Easy Wind Energy CenterTap 345kV #76003 Big Hill - #76005 Schneeman Draw circuit #1Easy Wind Energy Center, LLCWind241.1Jun 2029In study

Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.

Where are the flood maps for Schleicher County?

FEMA flood maps for Schleicher County

How does a project here connect to the grid?

Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.

Interconnection by market and utilityERCOT resource integration

What state and federal reviews can apply?

Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.

Statewide and federal contactsTexas decommissioning law

Check a specific property in Schleicher County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Open Quicksand Check

Other counties served by TCEQ Region 8

Coke · Concho · Crockett · Irion · Kimble · Mason · McCulloch · Menard · Reagan · Sterling · Sutton · Tom Green

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not legal advice. Found an error? Let us know.