Bexar County, Texas: solar, wind, and storage permits
Who to call and what to check for a solar, wind, or battery storage project in Bexar County. Texas has no statewide siting permit for solar or wind, so the key contacts are the appraisal district, state environmental offices, the grid operator, and the county itself.
Who handles property records and taxes in Bexar County?
The Bexar County appraisal district keeps parcel records and decides agricultural or wildlife valuation, which a solar or storage lease can end, triggering rollback taxes. The Texas Comptroller lists the district's and the county tax office's phone, email, address, and website, plus local taxing districts such as groundwater conservation districts.
Bexar County directory (Texas Comptroller)Lease rates and rollback taxes
Which TCEQ office covers Bexar County?
TCEQ Region 13, San Antonio
14250 Judson Rd, San Antonio TX 78233-4480
Main line: 210-490-3096 · Spills, 24 hours: 800-832-8224
Construction that disturbs 1 acre or more needs coverage under TCEQ's Construction General Permit (TXR150000) and a stormwater pollution prevention plan.
TCEQ region directoryConstruction stormwater permit
Does Bexar County have zoning or a solar permit?
Texas counties generally do not have zoning authority, and the state has no siting permit for solar or wind generation. Projects are usually shaped instead by site control, road use agreements with the county, tax agreements, and utility interconnection. If the county takes part in FEMA's flood insurance program, its floodplain administrator issues development permits in mapped flood zones. Ask the county judge's office or commissioners court about road use and any local requirements.
What energy projects are proposed in Bexar County?
ERCOT's August 2026 interconnection report lists 23 proposed energy projects in Bexar County (1 solar, 20 battery storage and 2 gas), about 5,170 MW in all. 10 of the 23 have a signed interconnection agreement, and 3 have been energized or approved to connect.
Got an offer? Check whether the company or project appears here. A listing means a developer asked ERCOT to study connecting it to the grid; many listed projects are never built, and projects further along are more likely to proceed.
Scroll the table sideways to see every column.
| Project and connection point | Developer | Type | MW | Projected in service | Stage |
|---|---|---|---|---|---|
| Padua Grid BESS Unit 3Tap #5395 O.W Sommer 138kV | Padua Grid 3, LLC | Battery storage (stand-alone) | 201.3 | May 2026 | Approved to connect |
| CPS AvR CT1 Rotor Replacement5475 Braunig 345kV | CPS Energy | Gas combined cycle | 11.3 | Aug 2026 | Approved to connect |
| CPS Energy AvR1CT2 Rotor Replacement5475 Braunig 345kV | CPS Energy | Gas combined cycle | 23.2 | Aug 2026 | Approved to connect |
| Bexar Martinez BESSTSP Station Name: Martinez | Bexar Martinez LLC | Battery storage (stand-alone) | 10.0 | Jan 2027 | Signed; security posted |
| El Patrimonio Solartap 138kV 5429 Trumbo - 5260 Leon Creek | Heritage Solar, LLC | Solar | 152.3 | Apr 2027 | Signed; security posted |
| Louisa Energy Storage138 kV Helotes (#5200) | VESI 49 LLC | Battery storage (stand-alone) | 102.8 | Mar 2029 | Signed; security posted |
| Taormina StorageTap 138kV VH Braunig (5025) to Valley Road 138kV (5465) | Taormina Storage Project LLC | Battery storage (stand-alone) | 231.9 | May 2029 | Signed; security posted |
| Alamo City BESSTap 138kV 5294 Martinez - 5110 JT Deely | ALAMO CITY ESS LLC | Battery storage (stand-alone) | 128.2 | Sep 2027 | Signed May 2025 |
| Riverwalk BESS5294 Martinez Substation 138kV | RWE Solar Developement, LLC | Battery storage (stand-alone) | 120.0 | Oct 2027 | Signed Aug 2026 |
| Lavender Storage ProjectTap 138kV Deely (bus 5110) - Laredo (bus 5255) | Lavender Storage Project LLC | Battery storage (stand-alone) | 231.9 | Sep 2029 | Signed Jun 2025 |
| Orbit Energy StorageTap 345 kV Calaveras Power Station (BUS #5400) to VON_ROSE (BUS #5475) | GCI Orbit Energy Storage, LLC | Battery storage (stand-alone) | 501.9 | Jun 2027 | In study |
| Ferdinand Grid BESS II5260 Leon Creek 138kV | Coval Infrastructure DevCo LLC | Battery storage (stand-alone) | 208.1 | Dec 2027 | In study |
| Quela BESSTap 138kV 5110 J.T. Deely - 5294 Martinez | BRP Quela BESS LLC | Battery storage (stand-alone) | 301.4 | Dec 2027 | In study |
| Horsepower BESSPOI is 138 kV Howard Substation (Bus# 5230) (SSWG bus name: HOWARD)... | Horsepower BESS, LLC | Battery storage (stand-alone) | 257.5 | Jan 2028 | In study |
| Howard Road BESS5231 HOWARD RD 345 kV | Project Fast Flow LLC | Battery storage (stand-alone) | 617.6 | Apr 2028 | In study |
| Caracara Energy Storage CenterTap 138kV 5055 Cagnon - 5346 Potranco | FRESH AIR ENERGY II, LLC | Battery storage (stand-alone) | 203.0 | Aug 2028 | In study |
| Bernice Energy Storage5135 ELMENDORF 138kV | Bernice Energy Storage LLC | Battery storage (stand-alone) | 402.8 | Feb 2029 | In study |
| Dorsey Road BESSTap 138 kV Chavanea (5085) - Palo Alto (5330). | Horizon Energy Storage Greenfield Project Holdings LLC | Battery storage (stand-alone) | 150.4 | Aug 2029 | In study |
| Otter BESS5378 SHEPHERD RD 138kV | GRS BESS TEXAS TEN, LLC | Battery storage (stand-alone) | 157.1 | Sep 2029 | In study |
| Mission Station Energy Storage ITap 345kV (Bus #5400) SPRUCE – (Bus #5475) VON_ROSE Ckt 1; | Mission Station LLC | Battery storage (stand-alone) | 375.0 | May 2030 | In study |
| Mission Station Energy Storage IITap 345kV (Bus #5400) SPRUCE – (Bus #5231) HOWARD_5 Ckt 1 | Mission Station LLC | Battery storage (stand-alone) | 375.0 | May 2030 | In study |
| Cado StorageTap 138 kV Line from Braunig East (#5030) to Highland Hills (#5205)... | Cado Storage, LLC | Battery storage (stand-alone) | 205.5 | Jun 2030 | In study |
| RUSH ESSTap 345 kV 5231 HOWARD_5 – 5400 SPRUCE | OCI Solar Power LLC | Battery storage (stand-alone) | 201.3 | Feb 2031 | In study |
Stage: In study means ERCOT is still studying the connection; Signed means the interconnection agreement is signed; security posted means the developer has also posted financial security and a notice to proceed; Energized and Approved to connect mean ERCOT has approved the project to energize or synchronize with the grid. "Self-limiting" batteries are reported as 0 MW because they are sized below the site's total capacity. Source: ERCOT Generator Interconnection Status (GIS) Report, August 2026. ERCOT prepares this report for planning purposes from data entered by developers and transmission providers, and notes it may contain errors or be out of date.
Where are the flood maps for Bexar County?
FEMA flood maps for Bexar County
How does a project here connect to the grid?
Most of Texas is on the ERCOT grid, but parts of the Panhandle and northeast Texas are in SPP, parts of east Texas are in MISO, and El Paso is in the western grid. The serving utility decides which process applies.
Interconnection by market and utilityERCOT resource integration
What state and federal reviews can apply?
Depending on the site: wetland permits from the U.S. Army Corps of Engineers, endangered species review through U.S. Fish and Wildlife, historic review through the Texas Historical Commission, wildlife comments from Texas Parks and Wildlife, and FAA notice for tall structures like wind turbines.
Statewide and federal contactsTexas decommissioning law
Check a specific property in Bexar County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.